The Capital Region

Pipes and Tunnels

The sewers and treatment plants built around the Bay; the District’s combined sewer overflow fell from 5,828 million gallons in 2005 to 253 million in 2025.

9 min read · 14 exhibits

The largest environmental works in the Capital Region over the past two decades are not wetlands or oyster reefs. They are sewer tunnels and treatment-plant upgrades: three tunnels under the District, nitrogen-removal plants at Blue Plains, Back River and Patapsco, Alexandria’s RiverRenew, and Hampton Roads’ plan to inject treated water into the Potomac aquifer. Most were built under consent decrees or state law, and ratepayers carry most of the cost.

This study sets out what was built and by whom, what the owners’ own records show each program changed, and who pays. The District, Maryland and Virginia are the comparison; Philadelphia, in the Delaware basin, and ALCOSAN in Pittsburgh, in the Ohio basin, appear only as labeled comparisons from outside the Bay. Contract figures are approved values from board resolutions and commission minutes, not payments. Modeled overflow volumes and reported discharges are kept apart, and each exhibit says which it shows.

What was built

13. The Anacostia tunnels opened in March 2018 and the Northeast Boundary Tunnel in September 2023; the Potomac River Tunnel is due February 8, 2030

Full size

Source. DC Water Board resolutions; HRSD Commission minutes; Baltimore Board of Estimates minutes; Virginia DEQ report RD662; DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond report RD1001 (2024); Philadelphia Year 10 plan; ALCOSAN 2026 budget.

Method. Bars run from contract award (or decree, order or plan year where no single contract governs) to the in-service date or, where work is unfinished, to the legal deadline (black tick) or the owner’s projected date (open circle); the James River SWIFT bar stops at October 2026 because no completion date was found. Values are the approved contract figure, HRSD’s stipulated price, or the owner’s program estimate where no single contract covers the work. Joint-venture values are whole-contract. Patapsco and Back River in-service dates are Maryland’s BayStat dates and may be year placeholders.

DC Water’s Clean Rivers program is the largest in the set. The Blue Plains and Anacostia tunnels went into service in March 2018; the Northeast Boundary Tunnel followed on September 15, 2023, eighteen months before its March 2025 deadline. DC Water’s Q2 2026 decree report records every dated enforceable requirement due to that point as completed on time. The Potomac River Tunnel, awarded in October 2023 at a not-to-exceed $819.7M, is due in operation on February 8, 2030; the builder’s schedule shows December 2029.

Hampton Roads Sanitation District (HRSD) is the other large buyer. Its James River SWIFT and nutrient upgrade, at a stipulated $534.1M, was 83.7% complete in June 2025, and Garney Companies holds the Nansemond SWIFT facility at $608.7M plus $85.9M for recharge wells. By the approved figures in board records, the ten largest contracts total $4.36 billion, and 7 of the ten went to joint ventures, none of which publishes member shares except the Potomac River Tunnel team. The one tunnel with a published closing figure, Blue Plains, finished at $318.7M against $330.6M awarded.

14. The Potomac River Tunnel, not to exceed $819.7M, is the largest wastewater contract in the region’s records; HRSD’s Nansemond SWIFT, $608.7M, is next

Full size

Source. DC Water Board resolutions 11-57, 13-56, 13-64, 17-45 and 23-54; HRSD Commission minutes, 2022–2025; Virginia DEQ report RD662 (2021); Water Tech Online (2013).

Method. Ranked by the figure approved: the original award for DC Water, AlexRenew and Baltimore, the stipulated price for HRSD design-build. The Potomac River Tunnel figure is a not-to-exceed ceiling. The Back River figure is from trade press and the RiverRenew figure from a state report. Coverage is four buyers; Richmond, Philadelphia and ALCOSAN contracts were not compiled.

What the District’s tunnels changed

By DC Water’s model, overflow to the District’s three rivers fell from 5,828 million gallons in 2005 to 253 million in 2025. Each year is run with its own rain, 44.38 and 35.56 inches at Reagan National, so part of the fall is a drier year. The Anacostia, where the tunnels are, accounts for most of the change; the Potomac, where the tunnel is under construction, carried 244.2 million gallons in 2025.

The tunnel system’s meters give a second reading. From March 2018 to December 2025 the Anacostia tunnels captured 19,579 million gallons and overflowed 1,658 million in 398 events, 92.2% captured (DC Water, February 2026). DC Water reported 89% capture for March to December 2018; calendar 2025, 1,803 million gallons captured and 5 million overflowed, works out to 99.7%. The two years are not like for like: 2018 was a record-wet 66.28 inches, 2025 had 35.56, and the Northeast Boundary Tunnel was added in between.

15. DC Water’s reports put the District’s overflow at 5,828 million gallons in 2005 and 253 million in 2025; 96.5% of the 2025 total now reaches the Potomac

Full size

Source. DC Water, combined sewer overflow quarterly reports, 2005–2025 (combined sewer system model and metered results); NOAA ACIS, Reagan National precipitation.

Method. Each year is the sum of four quarterly reports’ river subtotals, run with that year’s actual rain, so years are not normalized. Through 2017 every value is a model result. From 2018 DC Water publishes one figure per river that combines modeled outfalls with metered tunnel outfalls; the 2025 Anacostia value, 5.4 million gallons, is entirely metered, and the Potomac and Rock Creek values are modeled. The Anacostia tunnels entered service in March 2018 and the Northeast Boundary Tunnel in September 2023.

16. In 2025 the busiest Potomac outfall overflowed 46 times and the busiest Rock Creek outfall 27; on the Anacostia none overflowed more than once

Full size

Source. DC Water, combined sewer overflow quarterly reports, 2005–2025: number of overflows per outfall.

Method. For each river, the highest annual count at any one outfall, summed from four quarterly per-outfall counts: a lower bound on events, not a system-wide count. Counts are model results except at metered tunnel outfalls from 2018; the busiest 2025 Potomac outfall (028, 36th and M Streets) and Rock Creek outfall (036) are modeled. The 2012 Potomac (152) and Rock Creek (108) values are carried as published.

Maryland and Virginia

Patapsco’s reported nitrogen discharge fell 83% from 2009 to 2025 and Back River’s 78% from 2014 to 2024, after Baltimore’s two plants added nutrient removal. Both rose again in 2021–22: Back River discharged 2,379,886 lb in 2021 against a combined annual cap of 2,192,803 lb, during the permit violations that preceded the state’s 2023 consent decree. Maryland’s Bay Restoration Fund put $347.1 million into Back River’s upgrade and $145.5 million into Patapsco’s (MDE, January 2026).

The city’s sewer-overflow decree has moved more slowly. Baltimore reports 73 of 77 overflow structures eliminated by March 2026: 60 of the 62 named in the 2002 decree and 13 of 15 found since (Baltimore quarterly report 34). The last four, on the Jones Falls, carried most of the 2023–24 overflow volume, are projected for June 2028, and the city has asked for a July 2030 deadline. In December 2025 it proposed moving Phase II completion from 2030 to December 31, 2046.

17. Patapsco’s reported nitrogen discharge fell 83% from 2009 to 2025 and Back River’s 78% from 2014 to 2024; Back River exceeded its cap in 2021

Full size

Source. EPA ECHO, discharge monitoring reports: MD0021601 (Patapsco) and MD0021555 (Back River, outfalls 001 and 002), 2009–2025.

Method. Annual loads the plants reported: the December year-to-date or annual total on the discharge monitoring report (Patapsco 2009 is monthly load times days). Back River 2011 and 2016 lack a full-year figure and the line joins across them. Caps are the annual limit fields (Patapsco from 2015; Back River outfalls 001 and 002 summed, from 2018).

18. Baltimore’s Phase II Plan records 84 million gallons of wet-weather sewer overflow in 2020, 26 million in 2021 and 5.7 million in 2022

Full size

Source. City of Baltimore DPW, Modified Consent Decree Phase II Plan (January 2023); quarterly consent-decree reports, 2023–2025, Attachment 1.

Method. Reported overflows, not modeled. 2020–22 are the Plan’s own figures; 2023–25 are tallies of every wet-weather row in the quarterly listings, so the two halves come from different documents and possibly different wet-weather rules. Structures #67 and #72 carried 14.36 million gallons in 2023 and 31.83 million in 2024 (81% of the 2024 tally). Separately, the city’s model puts overflow over a 20-year typical rainfall at 2.4 billion gallons for 2002 conditions and 235 million in its “Baseline 2030” simulation.

HRSD’s delivered nitrogen to the James halved between 2017 and 2025, but 83.5% of the drop is one internal discharge point that reported no flow from January 2022, consistent with the Chesapeake-Elizabeth plant’s closure; the other points fell 15.3%. HRSD’s major-plant effluent TKN, a partial nitrogen measure, fell from 12.3 to 4.7 thousand lb a day between FY2011 and FY2025 (HRSD annual reports). Its SWIFT Research Center has recharged 1,062.1 million gallons into the Potomac aquifer since 2018, running at 31.0% of its one-million-gallon daily capacity in 2025; the full-scale James River plant has not yet reported recharge.

19. HRSD’s James River nitrogen fell from 3.72 million lb delivered in 2017 to 1.78 million in 2025; 83.5% of the drop is one point that stopped reporting

Full size

Source. EPA ECHO, Virginia Watershed General Permit aggregate VAN040090 (HRSD, James River basin), 2017–2025.

Method. Delivered load is reported effluent mass adjusted by Virginia’s delivery factors and summed across HRSD’s James basin plants; 2023–25 are sums of monthly loads. The light line excludes internal monitoring point 507 (2,098,993 to 1,777,836 lb), which reported 1,624,872 lb in 2017 and no discharge from January 2022. The limit fell from 4.55 to 3.55 million lb in 2022.

Richmond and Lynchburg run the oldest programs on the James. Richmond took overflow capture from 80% to 91% in three phases between 1970 and 2021 for $117 million, $127 million and $68 million in the dollars of the day. Its final plan, due July 1, 2035, is estimated at $575M for 96% capture; in 2021 the city priced a 99% alternative at $1.3 billion in 2021 dollars. The two figures differ in dollar basis and scope, so the gap, about 56%, is not a like-for-like saving; the city describes $575 million as 40% of its 2022 estimate and is seeking state grants for most of it. Lynchburg reports 115 of its 132 original overflow points closed and overflow volume down 93% after $307 million spent since 1994; its $103.9M Blackwater storage tunnel was mined in July 2026.

20. Richmond’s final plan buys 96% overflow capture by 2035 for an estimated $575 million; a 99% alternative was priced at $1.3 billion in 2021 dollars

Full size

Source. City of Richmond DPU, presentation to the State Water Commission (December 2021); City of Richmond report to the General Assembly RD1001 (2024). Capture rates are the city’s modeled annual estimates.

Method. Phase costs are the city’s figures restated in 2021 dollars. The Final Plan estimate is in mid-point-of-construction dollars and covers four projects plus green infrastructure; the 99% figure is a 2021-dollar alternative with wider scope. Deadlines (July 1, 2027 and July 1, 2035) are set by state law.

Who pays

Ratepayers pay for nearly all of it. DC Water bills the tunnels through its Clean Rivers Impervious Area Charge, which rose from $1.24 a month per equivalent residential unit in FY2009 to $25.18 in FY2018 and is $24.23 in FY2026; the average residential bill rose 129% between FY2012 and FY2025, from $59.11 to $135.55 a month. Federal appropriations for the program total $220.3 million since FY2006, about 8.5% of the $2.6 billion program estimate, and fell to $2.673 million in FY2026. DC Water’s proposed FY2027 budget puts the cost to complete at $1.1 billion (DC Water, FY2027 wholesale customer presentation, January 2026, p. 6).

HRSD’s treatment charge rose 249% between FY2011 and FY2027, from $2.82 to $9.84 per hundred cubic feet, and 9.0% in the last year alone, from $9.03 in FY2026, and its FY2027 budget forecasts the average monthly bill rising from $54.12 to $110.80 by FY2046. Outside the Bay, ALCOSAN’s average bill in Pittsburgh went from $479.44 to $719.20 a year in fixed 7% steps under its 2020 decree, while the estimated cost of its active capital program reached $4.66B in its 2026 budget. Lynchburg reports $17,600 spent per household since 1994 and 24% of households paying more than 4% of income for sewer service.

21. DC Water’s Clean Rivers charge rose from $1.24 a month in FY2009 to $25.18 in FY2018 and is $24.23 in FY2026; the average bill was $135.55 in FY2025

Full size

Source. DC Water, FY2025 Annual Comprehensive Financial Report, statistical section, Exhibit 8; FY2015 CAFR Exhibit 8; DC Water, Impervious Area Charge (FY2026 rate).

Method. The charge is billed per equivalent residential unit (ERU), 1,000 square feet of impervious area. The average bill is DC Water’s calculated average residential customer, all charges included; its consumption basis changes at FY2019 (6.2 to 5.42 hundred cubic feet a month). The charge was 11.2% of that bill in FY2012, 25.3% in FY2018 and 15.7% in FY2025.

22. HRSD’s treatment charge rose 249% from FY2011 to FY2027, to $9.84 per hundred cubic feet; outside the Bay, ALCOSAN’s bill rose 50% in 2020–26

Full size

Source. HRSD rate schedule, FY2027 and FY2020 CAFR; HRSD FY2027 Operating Budget (bill forecast); ALCOSAN 2025 Consulting Engineer’s Report and 2026 Budget and audited financial statements, 2021–2025.

Method. HRSD’s charge is the regional treatment charge per CCF (748 gallons) only; localities bill collection and water separately. ALCOSAN, in the Ohio River basin, is shown for comparison; its bill assumes 12,000 gallons a quarter and 2026 is the adopted budget-year rate. Nominal dollars.

23. Clean Rivers appropriations peaked at $20.0 million in FY2010, were $2.673 million in FY2026 and total $220.3 million, about 8.5% of the estimate

Full size

Source. DC Water, Long Term Control Plan consent-decree quarterly report, Q2 2026, grant funding table.

Method. FY2007 is not listed in the report (n/l). The share uses the $2.6 billion program estimate DC Water gave in 2009–2015; its own statements range from $2.6 billion to $2.8 billion with no price year.

Green infrastructure, planned and built

Green infrastructure has cost more per acre than DC Water planned. Rock Creek Project A came in at about $1.17 million per impervious acre managed, 3.9 to 4.7 times the 30% scenarios in the 2015 plan, which were priced on a 2012 construction-cost basis; the multiples are not inflation-adjusted. A 2020 stipulation replaced most of the required green acres with storage: the Potomac’s 133 acres became a tunnel of at least 40 million gallons, and Rock Creek’s 365 became 92 plus a 4.2 million-gallon storage facility, now the Piney Branch tunnel. DC Water reports 50.53 Rock Creek acres delivered through mid-2026.

Philadelphia, outside the Bay in the Delaware basin, went the other way and made green infrastructure the core of its plan. Its modeled overflow reduction at Year 10 was 3,080 million gallons a year against 2,044 required, and modeled capture rose from 62% in 2011 to 70.7% in 2021 against an 85% goal for 2036. Both are model results on typical-year rain, and they are reductions from the 2011 baseline, not overflow volumes.

24. Rock Creek Project A cost about $1.17 million per impervious acre managed, 3.9 to 4.7 times the 2015 plan’s 30% scenarios of $249,553 and $298,532 an acre

Full size

Source. DC Water, Long Term Control Plan Modification for Green Infrastructure (May 2015), Technical Memorandum 7 and Appendix K; Potomac River Green Infrastructure Practicability Assessment (August 2020), Table 2-8; Rock Creek Project C description (2024).

Method. Built figures are capital cost (design and construction) divided by impervious acres managed, in nominal dollars of the build years; planning figures are construction-cost unit rates on a 2012-dollar basis. The 2024 Rock Creek C figure is the midpoint of a $600,000–$825,000 range.

25. Outside the Bay, Philadelphia reports 3,903 greened acres in June 2026 against a Year 15 requirement of 3,812, on a new method since fiscal 2022

Full size

Source. Philadelphia Water Department, NPDES CSO annual reports FY17–FY26; Green City, Clean Waters Year 10 Evaluation and Adaptation Plan; PADEP Consent Order and Agreement (2011). Requirements are legal; acres are self-reported.

Method. A greened acre is an acre of impervious area whose first inch of runoff is managed. From FY22 the city also credits infiltration and slow release, so FY22–FY26 are not on the same method as FY16–FY21; the Year 10 plan restated December 2021 at 2,196 acres on the old method against 2,148 required. Year 25 is 9,564 acres in 2036.

What is still ahead

The Potomac River Tunnel is due in operation on February 8, 2030, and the Rock Creek storage tunnel on November 23, 2029; with them, DC Water’s plan reaches its last legal milestone. Richmond’s interim projects are due July 1, 2027 and its final plan July 1, 2035. HRSD expects its federal decree to be terminated and its first full-scale SWIFT phase to finish in spring 2029. Philadelphia’s Year 15 standards fall due in April 2027 and its 85% capture goal in 2036.

Two things are unsettled. Baltimore has asked to move its sewer decree’s completion from 2030 to the end of 2046, and the decree report says further discussion with EPA and Maryland may be needed. And none of the tunnel programs has yet published a full year of measured results with its final tunnel in service; DC Water’s quarterly reports after 2030 will show what the Potomac tunnel changes.

26. The Potomac River Tunnel is due in operation on February 8, 2030 and Richmond’s final plan on July 1, 2035; Baltimore proposes December 31, 2046

Full size

Source. DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond RD1001 (2024); Philadelphia FY26 annual report; HRSD and Lynchburg project pages.

Method. Filled dots are legal deadlines (consent decree, order, state law); open dots are dates the owner projects or proposes, which are not binding. Baltimore’s 2046 date is its December 2025 revised Phase II Plan proposal. The Potomac River Tunnel’s enforceable date is February 8, 2030, with a tracking date of March 23, 2030.

Limitations (11)

  • Unverified. Final costs. Contract values are approved figures, not payments. Only the Blue Plains Tunnel has a published final contract cost ($318.7 million against $330.6 million awarded); the Northeast Boundary Tunnel’s $583 million is a project figure from DC Water’s completion release, not the $580.0 million contract value, and no final cost was found.
  • Conflicting sources. The Potomac River Tunnel’s in-operation date. DC Water’s decree report gives February 8, 2030 as enforceable, with a tracking date of March 23, 2030; an independent check of the overflow series cites March 23. The earlier date is used here.
  • Coverage. Joint-venture member shares, which are unpublished for every joint venture in Exhibit 14 except the Potomac River Tunnel team.
  • Coverage. Contracts outside four buyers. Baltimore Board of Estimates minutes for 2013–2022 were not found, DC Water board documents for February 2024 to December 2025 are not online, and Richmond, Philadelphia, Lynchburg and ALCOSAN contracts were not compiled, so the Rock Creek storage tunnel’s builder and value are missing.
  • Unverified. The dates Back River and Patapsco entered nutrient-removal service, which come from Maryland’s BayStat table and may be year placeholders.
  • Conflicting sources. Baltimore’s 2020–22 and 2023–25 overflow figures, which come from different documents and possibly different wet-weather rules; the city has also restated its Phase I cost between $1,032.6 million and $1,036.0 million without explanation.
  • Unverified. Philadelphia’s Year 5 overflow-reduction requirement, which was not found in any document opened, and its Year 15 overflow result, which has not been reported.
  • Unverified. Series not independently re-derived: overflow-event counts before 2025, Baltimore’s 2023–25 overflow tallies, HRSD’s SWIFT and TKN series, ALCOSAN’s capital estimate, Lynchburg’s figures and the 2009–2024 points of the Anacostia volume series. Lynchburg’s count of closed overflow points is 110, 112 or 115 depending on the city page, and its tunnel cost is given as $100 million (2023), $103.9 million and $104 million (2026).
  • Unverified. Addresses for six documents the source lines name but no record located at port: HRSD’s annual reports and FY2020 financial report, ALCOSAN’s audited statements for 2022–2025, and DC Water’s FY2015 financial report, Rock Creek Project C description and Northeast Boundary Tunnel completion release; nor for Philadelphia’s NPDES CSO annual reports for FY17–FY25. They are listed by name in the Sources.
  • Unverified. The Reagan National precipitation record behind Exhibit 15’s rain totals: NOAA’s ACIS station data is a query service with no address for the record itself, so it is named, not linked.
  • Coverage. Measured results after completion: none yet for RiverRenew (in service July 2026) or the full-scale James River SWIFT plant, and no measured overflow series for ALCOSAN or Lynchburg.

Sources (22)

  1. DC Water: Board meeting package, October 5, 2023 (Resolution 23-54, Potomac River Tunnel); Resolutions 17-42 through 17-48 (Northeast Boundary Tunnel). 2017; Board-approved resolutions, May 2011 (Blue Plains Tunnel); Board resolution, May 2013 (Anacostia River Tunnel); Combined sewer overflow quarterly reports, 2005–2025 (first quarter 2005); Combined sewer overflow quarterly report, fourth quarter 2025; Environmental Quality and Operations Committee package, February 19, 2026 (tunnel performance); Long Term Control Plan consent-decree quarterly report, Q2 2026. July 27, 2026; FY2025 Annual Comprehensive Financial Report, statistical section; Impervious Area Charge; Long Term Control Plan Modification for Green Infrastructure. May 2015; FY2027 Wholesale Customer Presentation. January 2026 (p. 6, the cost to complete Clean Rivers); Approved resolutions, June 6, 2013 (tunnel dewatering pump station); Potomac River Green Infrastructure Practicability Assessment. August 2020
  2. HRSD: Commission minutes, May 24, 2022 (James River SWIFT stipulated price); Commission minutes, July 22, 2025 (Nansemond SWIFT stipulated price); FY2027 rate schedule; FY2027 Operating Budget; SWIFT Research Center water quality reports; Commission minutes, February 28, 2023 (Nansemond nutrient upgrade, Phase II); SWIFT program page
  3. EPA ECHO: Effluent charts, VAN040090 (HRSD James River aggregate); Effluent charts, MD0021601 (Patapsco); Effluent charts, MD0021555 (Back River)
  4. Baltimore Board of Estimates: Minutes, June 6, 2012 (Patapsco nitrification filters)
  5. Water Tech Online: “Board approves $263.5 million project to expand and renovate wastewater facility.” August 2013
  6. City of Baltimore DPW: Modified Consent Decree Phase II Plan. January 2023; Modified Consent Decree quarterly report 34, period ending March 31, 2026; Sanitary sewer consent decree quarterly reports
  7. Maryland Department of the Environment: Bay Restoration Fund annual status report. January 2026; Bay Restoration Fund wastewater update for BayStat. 2026
  8. Virginia DEQ: Report RD662 to the General Assembly (RiverRenew). 2021
  9. City of Richmond DPU: Combined sewer system presentation to the State Water Commission. December 1, 2021
  10. City of Richmond: Report to the General Assembly, RD1001. 2024
  11. City of Lynchburg: ARPA CSO white paper; Drill-and-blast phase of Blackwater CSO tunnel project complete (project news)
  12. Philadelphia Water Department: FY26 NPDES CSO annual report; Long Term Control Plan reporting page; Green City, Clean Waters Year 10 Evaluation and Adaptation Plan
  13. ALCOSAN: 2025 Consulting Engineer’s Report and 2026 Budget; Audited financial statements, 2021
  14. NOAA Regional Climate Centers: ACIS station data, Washington Reagan National precipitation
  15. HRSD: annual reports (effluent TKN, FY2011–FY2025)
  16. HRSD: FY2020 Comprehensive Annual Financial Report
  17. ALCOSAN: audited financial statements, 2022–2025
  18. DC Water: FY2015 Comprehensive Annual Financial Report, Exhibit 8
  19. DC Water: Rock Creek Project C description (2024)
  20. DC Water: Northeast Boundary Tunnel completion release (2023)
  21. Philadelphia Water Department: NPDES CSO annual reports, FY17–FY25
  22. Pennsylvania Department of Environmental Protection: Consent Order and Agreement with the City of Philadelphia, June 1, 2011