The Potomac River Tunnel is due in operation on February 8, 2030 and Richmond’s final plan on July 1, 2035; Baltimore proposes December 31, 2046
Source. DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond RD1001 (2024); Philadelphia FY26 annual report; HRSD and Lynchburg project pages.
Method. Filled dots are legal deadlines (consent decree, order, state law); open dots are dates the owner projects or proposes, which are not binding. Baltimore’s 2046 date is its December 2025 revised Phase II Plan proposal. The Potomac River Tunnel’s enforceable date is February 8, 2030, with a tracking date of March 23, 2030.
| Item | Date | Type |
|---|---|---|
| DC: Potomac tunnel boring machine starts south drive | Dec 2026 | projected or proposed |
| Philadelphia (outside Bay): Year 15 standards | Apr 1, 2027 | legal deadline |
| Baltimore plants: decree final confirmation report | Jun 22, 2027 | legal deadline |
| Richmond: Interim Plan, 10 projects | Jul 1, 2027 | legal deadline |
| Lynchburg: Blackwater tunnel complete | summer 2027 | projected or proposed |
| Baltimore: last four overflow structures built | Jun 10, 2028 | projected or proposed |
| HRSD: first full-scale SWIFT phase complete | spring 2029 | projected or proposed |
| DC: Rock Creek storage tunnel in operation | Nov 23, 2029 | legal deadline |
| DC: Potomac River Tunnel in operation | Feb 8, 2030 | legal deadline |
| Baltimore: sewer decree Phase II, current deadline | Dec 31, 2030 | legal deadline |
| Richmond: Final Plan, 96% capture | Jul 1, 2035 | legal deadline |
| Philadelphia (outside Bay): Year 25, 85% capture | 2036 | legal deadline |
| HRSD: Rehabilitation Action Plan Phase II ends | Dec 31, 2040 | legal deadline |
| Baltimore: Phase II completion as proposed | Dec 31, 2046 | projected or proposed |