From Study XXI, Exhibit 26

The Potomac River Tunnel is due in operation on February 8, 2030 and Richmond’s final plan on July 1, 2035; Baltimore proposes December 31, 2046

Source. DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond RD1001 (2024); Philadelphia FY26 annual report; HRSD and Lynchburg project pages.

Method. Filled dots are legal deadlines (consent decree, order, state law); open dots are dates the owner projects or proposes, which are not binding. Baltimore’s 2046 date is its December 2025 revised Phase II Plan proposal. The Potomac River Tunnel’s enforceable date is February 8, 2030, with a tracking date of March 23, 2030.

ItemDateType
DC: Potomac tunnel boring machine starts south driveDec 2026projected or proposed
Philadelphia (outside Bay): Year 15 standardsApr 1, 2027legal deadline
Baltimore plants: decree final confirmation reportJun 22, 2027legal deadline
Richmond: Interim Plan, 10 projectsJul 1, 2027legal deadline
Lynchburg: Blackwater tunnel completesummer 2027projected or proposed
Baltimore: last four overflow structures builtJun 10, 2028projected or proposed
HRSD: first full-scale SWIFT phase completespring 2029projected or proposed
DC: Rock Creek storage tunnel in operationNov 23, 2029legal deadline
DC: Potomac River Tunnel in operationFeb 8, 2030legal deadline
Baltimore: sewer decree Phase II, current deadlineDec 31, 2030legal deadline
Richmond: Final Plan, 96% captureJul 1, 2035legal deadline
Philadelphia (outside Bay): Year 25, 85% capture2036legal deadline
HRSD: Rehabilitation Action Plan Phase II endsDec 31, 2040legal deadline
Baltimore: Phase II completion as proposedDec 31, 2046projected or proposed

Download pipes-and-tunnels-14-what-is-ahead.csv

Download SVG · CSV. Data and chart licensed CC BY 4.0.