Richmond’s final plan buys 96% overflow capture by 2035 for an estimated $575 million; a 99% alternative was priced at $1.3 billion in 2021 dollars
Source. City of Richmond DPU, presentation to the State Water Commission (December 2021); City of Richmond report to the General Assembly RD1001 (2024). Capture rates are the city’s modeled annual estimates.
Method. Phase costs are the city’s figures restated in 2021 dollars. The Final Plan estimate is in mid-point-of-construction dollars and covers four projects plus green infrastructure; the 99% figure is a 2021-dollar alternative with wider scope. Deadlines (July 1, 2027 and July 1, 2035) are set by state law.
| Step | Cost ($ million) | Dollar basis | Basis |
|---|---|---|---|
| Phase 1, 1970–88: 80% capture | 385 | 2021 dollars | estimated; capture modeled |
| Phase 2, 1988–2002: 85% | 226 | 2021 dollars | estimated; capture modeled |
| Phase 3, 2002–21: 91% | 102 | 2021 dollars | estimated; capture modeled |
| Interim Plan, due 2027: 92% | 33.1 | 2021 dollars | estimated; capture modeled |
| Final Plan, due 2035: 96% | 575 | mid-construction dollars (2024 estimate) | estimated; capture modeled |
| 99% alternative (2021) | 1,300 | 2021 dollars | estimated; capture modeled |
Download pipes-and-tunnels-08-richmond-cso-cost-and-capture.csv