From Study XXI, Exhibit 20

Richmond’s final plan buys 96% overflow capture by 2035 for an estimated $575 million; a 99% alternative was priced at $1.3 billion in 2021 dollars

Source. City of Richmond DPU, presentation to the State Water Commission (December 2021); City of Richmond report to the General Assembly RD1001 (2024). Capture rates are the city’s modeled annual estimates.

Method. Phase costs are the city’s figures restated in 2021 dollars. The Final Plan estimate is in mid-point-of-construction dollars and covers four projects plus green infrastructure; the 99% figure is a 2021-dollar alternative with wider scope. Deadlines (July 1, 2027 and July 1, 2035) are set by state law.

StepCost ($ million)Dollar basisBasis
Phase 1, 1970–88: 80% capture3852021 dollarsestimated; capture modeled
Phase 2, 1988–2002: 85%2262021 dollarsestimated; capture modeled
Phase 3, 2002–21: 91%1022021 dollarsestimated; capture modeled
Interim Plan, due 2027: 92%33.12021 dollarsestimated; capture modeled
Final Plan, due 2035: 96%575mid-construction dollars (2024 estimate)estimated; capture modeled
99% alternative (2021)1,3002021 dollarsestimated; capture modeled