The Capital Region

The Bay Scorecard

How the Chesapeake cleanup is graded against its Total Maximum Daily Load, the legal pollution limit; in 2025 it had made 57% of the nitrogen cut required.

9 min read · 12 exhibits

The Chesapeake Bay cleanup reached its 2025 deadline with one of three pollutants on target. In the Bay Program’s 2025 model run, released in August 2026, the seven watershed jurisdictions had made 57% of the nitrogen reduction required between 2009 and the 2025 interim target, 90% of the phosphorus reduction and 100% of the sediment reduction (EPA, 2025 Assessment). Nitrogen, the pollutant furthest behind, is most of what remains.

Two instruments set the targets, and they are easy to confuse. The Bay total maximum daily load (TMDL), set by EPA on December 29, 2010 under the Clean Water Act, is the legal pollution limit, with allocations to each jurisdiction (EPA, TMDL executive summary). The 2025 date is not in it as an enforceable deadline: it is the partnership’s goal, carried by the voluntary Chesapeake Bay Watershed Agreement and EPA’s accountability framework, of having all practices in place by 2025, with 60% of the reductions by 2017 (EPA, 2025 Assessment). EPA scores progress against the partnership’s 2025 interim targets, not against the 2010 allocations, which were set on an older model and are not comparable with today’s loads.

Everything on the scorecard is modeled. The loads are estimates from the Phase 6 watershed model, run each year with the practices the jurisdictions report, against fixed average weather. The rivers and the Bay itself are measured separately, and this study keeps the two apart.

The 2025 score

1. In the 2025 model run the watershed had made 57% of the required nitrogen reduction, 90% of the phosphorus and 100% of the sediment

Full size

Source. EPA, 2025 Assessment of the Chesapeake Bay Program partnership’s progress toward the 2025 water quality goal (August 13, 2026); Chesapeake Bay Program, 2025 Modeled Load Reduction Indicator workbook (modeled).

Method. Percent achieved = (2009 load − 2025 load) ÷ (2009 load − 2025 interim target), capped at 100%. Phase 6 watershed model with average hydrology. EPA’s text prints the 2025 phosphorus load as 12.8 million lb, which is the target; the Bay Program release and workbook give 13.2.

The percentage is not the load divided by the goal. It is the share of the required cut that has been made. Nitrogen reaching the Bay fell from 297.1 million lb in 2009 to 252.7 million lb in 2025, 15.0%; the 2025 target is 219.5 million lb, so 44.4 million lb of a required 77.6 million lb has come off, and 33.1 million lb remains. Phosphorus has 0.4 million lb to go. Sediment is 1.0 billion lb below its target and scores 100%.

2. Nitrogen has come down 44.4 million lb of the 77.6 million lb a year required since 2009; 33.1 million lb remains

Full size

Source. Chesapeake Bay Program, progress release of August 6, 2026; 2025 Modeled Load Reduction Indicator workbook; EPA, 2025 Assessment (modeled).

Method. Each line has its own scale. Totals include atmospheric deposition to tidal water; the targets are the 2025 interim targets with changing environmental conditions set by the partnership in 2023.

By jurisdiction the score splits in two. The District, Maryland and Virginia, the region this publication covers, are at or near their targets: the District at 100% on all three pollutants, Maryland at 99% of its nitrogen reduction and 100% on the other two, Virginia at 84% for nitrogen, 89% for phosphorus and 100% for sediment. West Virginia is at 100% throughout. Pennsylvania stands at 15% for nitrogen and New York at 62%. Delaware scores 0% on nitrogen because its modeled load rose: 6.61 million lb in 2009, 6.73 million lb in 2025.

3. The District and West Virginia met all three 2025 targets; Maryland stood at 99% for nitrogen, Virginia at 84% and Pennsylvania at 15%

Full size

Source. EPA, 2025 Assessment, table of percent completion (p. 3) (modeled).

Method. Bars cap at 100%. Delaware’s 0% means its modeled nitrogen load rose between 2009 and 2025. The Conowingo watershed implementation plan, scored separately for the extra load the full reservoir now passes, stood at 3% for nitrogen and is not in the bars.

Pennsylvania is most of what is left. Its modeled nitrogen load was 107.3 million lb in 2025 against a target of 77.1 million lb, 30.2 million lb over. Summing the jurisdictions that missed, the shortfall is 34.9 million lb a year, and Pennsylvania’s share of it is 86.5%. Virginia is 2.6 million lb over and Maryland 0.16 million lb. Pennsylvania’s load also rose between 2024 and 2025, from 104.5 to 107.3 million lb, which accounts for the slip in the Bay-wide nitrogen score. EPA notes that most of the remaining reductions in the jurisdictions’ own plans are to come from agriculture.

4. Pennsylvania was 30.2 million lb a year over its 2025 nitrogen target, 86.5% of the 34.9 million lb by which the jurisdictions that missed fell short

Full size

Source. Chesapeake Bay Program, 2025 Modeled Load Reduction Indicator workbook, Overview of States (modeled; computed here).

Method. Load minus target for each jurisdiction. Jurisdictions below target are not credited against those above it, so the 34.9 million lb is a sum of shortfalls, not the Bay-wide gap of 33.1 million lb, which nets them and includes atmospheric deposition.

Forty years in the model

Run back to 1985 on the same model, the land-based nitrogen load fell from 333.3 million lb to 237.1 million lb, 29%, and 66% of that fall came before the 2009 baseline, when the load was 270.1 million lb. Most of it was wastewater: sewage plants went from 94.5 to 26.5 million lb with nutrient-removal upgrades. Agriculture fell 25% and is still the largest source, 50% of the 2025 land-based load.

Two sources grew. Nitrogen from developed land rose from 27.5 to 40.1 million lb, 46%, and from septic systems from 5.45 to 7.81 million lb, 43%.

5. Modeled nitrogen from developed land (+46%) and septic systems (+43%) rose from 1985 to 2025; wastewater fell 72% and agriculture 25%

Full size

Source. Chesapeake Bay Program, Phase 6 watershed model (CAST) annual progress scenarios, 1985–2025; 1985, 2009 and 2025 checked against the 2025 Modeled Load Reduction Indicator workbook (modeled).

Method. Every year is run with fixed 1991–2000 hydrology and with atmospheric deposition held at its 2025 allocation level, so the change reflects practices, sources and land use, not weather or the actual decline in air deposition. Land-based sectors include wastewater and septic; deposition straight to tidal water is excluded.

The same model shows where the cuts were made. Modeled nitrogen from the District fell from 6.48 to 1.47 million lb between 1985 and 2025, almost all of it in wastewater. Maryland’s fell from 85.2 to 46.4 million lb and Virginia’s from 84.4 to 54.6. Pennsylvania’s fell from 122.4 to 107.3 million lb and is now 45% of the land-based total.

6. Modeled nitrogen fell 77% from the District, 46% from Maryland and 35% from Virginia, 1985–2025, but 12% from Pennsylvania, now 45% of the load

Full size

Source. Chesapeake Bay Program, Phase 6 watershed model (CAST) progress scenarios; 1985 and 2025 checked against the 2025 Modeled Load Reduction Indicator workbook (modeled).

Method. Loads are delivered to tidal water, so a pound applied far upstream counts only as the share of it that reaches the Bay. Same fixed hydrology and air deposition as Exhibit 5.

The history moves with the model. Each annual run is scored on the model version current at the time, and when the model is updated the past is rescored. Bay-wide nitrogen progress was published as 57% for 2023, 59% for 2024 and 57% for 2025; the 2023 figure used a 2009 baseline of 297.8 million lb and the later two 297.1. Phosphorus jumped from 67% to 92% in one year, reflecting the 2024 model update rather than a year of implementation. Pennsylvania’s nitrogen score was published as 29% for 2023 and 15% for 2025, on different versions. Within the current version the 2024-to-2025 step is real: the workbook puts Bay-wide nitrogen at 58.6% for 2024 and 57.3% for 2025, as agricultural nitrogen rose.

7. Bay-wide nitrogen was published as 57%, 59% and 57% for 2023 to 2025; phosphorus jumped from 67% to 92% with a model update

Full size

Source. Chesapeake Bay Program annual progress releases, 2016–2026, including May 2, 2024, June 3, 2025 and August 6, 2026; EPA, 2025 Assessment (modeled).

Method. Each bar is the figure published at the time, on that year’s model; the bars are not one series. Bay-wide percentages for the 2017 and 2018 runs were not found and are left out. The 2015 and 2016 runs used the Phase 5 model.

What the rivers and the Bay show

The model is checked against the rivers. USGS samples the nine largest tributaries where they reach tide, stations that drain about 78% of the watershed, and estimates loads from the samples and daily flow. To compare decades it removes the effect of wet and dry years statistically; the result, the flow-normalized load, is a statistical estimate, not a measured total. By that measure nitrogen at the nine stations fell from 242 million lb in water year 1985 to 174 million lb in 2025, 28%, close to the model’s 29% for the land-based load. The actual annual load swung between 81 million lb (2002) and 414 million lb (2004) with river flow. The two series cover different areas and are not the same quantity, so the agreement is in direction and rough size only.

8. Flow-normalized nitrogen at the nine fall-line stations fell 28% from 1985 to 2025, and the model’s land-based load 29%

Full size

Source. Left: Chesapeake Bay Program, Phase 6 watershed model (CAST) progress scenarios (modeled). Right: USGS River Input Monitoring, annual loads table, water year 2025, flow-normalized (statistical estimate) and Kalman-adjusted annual loads.

Method. Flow-normalized loads are WRTDS statistical estimates from monitoring samples, with year-to-year flow removed; the first and last years carry the most uncertainty. The stations exclude the 22% of the watershed below the fall line and deposition to tidal water.

Station by station the rivers differ. At the Susquehanna, below Conowingo Dam, flow-normalized nitrogen is 33% lower than in 1985, phosphorus is nearly unchanged (−3%) and sediment is 22% higher, consistent with EPA’s finding that the reservoir behind the dam no longer traps sediment and nutrients (EPA, 2025 Assessment). The Potomac at Chain Bridge is lower on all three, though USGS rates its 41-year sediment decline only as likely. The Patuxent, in Maryland, shows the steepest fall: nitrogen −69%, phosphorus −63%.

9. Flow-normalized nitrogen is 33% below 1985 on the Susquehanna, 17% on the Potomac and 69% on the Patuxent; Susquehanna sediment is 22% higher

Full size

Source. USGS River Input Monitoring, annual loads table, water year 2025, flow-normalized loads (statistical estimate).

Method. Each panel has its own scale; nitrogen and phosphorus in million lb, sediment in million short tons; rises are drawn in green. The Susquehanna’s 1985 sediment value is its series minimum and its peak came in 2008, so the endpoint change overstates the trend.

The test that matters legally is the Bay itself. The jurisdictions’ water-quality standards, adopted under the Clean Water Act, set criteria for dissolved oxygen, water clarity or underwater grasses, and chlorophyll a in each part of the tidal Bay; the TMDL exists to bring all of it into attainment. In 2021–23, 29.4% of the tidal waters met their standards, down slightly from 29.8% in 2020–22 (Chesapeake Bay Program, September 3, 2025). The high was 42.2% in 2015–17; the 1985–87 level was 26.5% (STAC, 2023). The Bay Program attributes the drop to the wet years of 2018 and 2019 and reports slow recovery since (Bay Barometer 2024–2025). No assessment for 2022–24 had been published by mid-October 2026, later than in past years.

10. 29.4% of the Bay’s tidal waters met their water-quality standards in 2021–23, against a high of 42.2% in 2015–17 and a legal goal of 100%

Full size

Source. Chesapeake Bay Program, Bay Barometer 2024–2025 (chart values, rounded); Chesapeake Bay Program release of September 3, 2025 (monitored).

Method. Bars are the Barometer’s rounded values; the text uses the decimals published at release. Attainment combines dissolved oxygen, water clarity or underwater grass acreage, and chlorophyll a over three years. The 2018–20 value was restated from 29.6% to 28.9%.

After the deadline

The partnership did not let the target lapse. On December 2, 2025 the Chesapeake Executive Council approved a revised Watershed Agreement with four goals and 21 outcomes, most dated 2040 (Chesapeake Bay Watershed Agreement, as amended 2025). For water quality it keeps the current targets, commits the partnership to revise the planning targets by December 31, 2030, and asks for new or revised watershed implementation plans to meet them by 2040, with a formal reassessment that year. A midpoint check in 2033 appears in Maryland’s announcement but not in the Agreement text. The Agreement is voluntary; the TMDL is the legal framework, and no EPA backstop decision on the missed 2025 targets was found.

Federal money has been roughly level since fiscal 2023. EPA’s Chesapeake Bay Program line was $93.0 million enacted for fiscal 2026, against $50.0 million in fiscal 2010; the fiscal 2027 request is $91.8 million (EPA, FY2027 Congressional Justification, Tab 04). Spending differs from appropriations year to year: $107.8 million in fiscal 2024, and $86.9 million in fiscal 2025 against $92.0 million enacted. Requests have been lower than Congress’s figure in several years: zero for fiscal 2018 and $7.3 million for 2019 to 2021.

11. EPA’s Chesapeake Bay Program line was $93.0 million enacted for fiscal 2026, against $50.0 million in fiscal 2010; the 2027 request is $91.8 million

Full size

Source. EPA, FY2027 Congressional Justification, Tab 04; EPA, FY2026 Budget in Brief and earlier Budgets in Brief (budgeted and reported).

Method. Dots without a line are the President’s requests. Enacted levels for fiscal 2011 and 2013–2015 were not found and are left as gaps. “Spent” is EPA’s final actuals, which it does not define further. Infrastructure-law money ($47.6 million in fiscal 2024) is separate and not drawn.

Two federal changes came after the deadline. Executive Order 14428, signed on September 16, 2026 and published on September 21, revokes Executive Order 13508 of 2009 on Chesapeake Bay protection and restoration (91 FR 59975). It directs agencies to move funding away from activities that do not show measurable progress, and directs EPA to assess the cost of local stormwater fees, look for approaches that do not raise residents’ costs and “take measures to encourage the repeal or rescission” of those fees. Its operative verbs are assess, explore and encourage, implementation is subject to appropriations, and it does not mention the TMDL. EPA had published no implementing notice by mid-October 2026.

What comes next is mostly process. The current two-year milestone period runs through 2027; the partnership expects a new generation of the model, Phase 7, around 2028, and past model updates have changed the historical scores (Exhibit 7); revised planning targets are due by the end of 2030 and plans to meet them by 2040. Underwater grasses, crabs, oysters and fish are scored separately and are left to another study.

12. The revised Agreement moves the water-quality horizon to 2040; planning targets are to be revised by December 31, 2030

Full size

Source. EPA, Chesapeake Bay TMDL executive summary (2010); EPA, 2025 Assessment; Chesapeake Bay Watershed Agreement, as amended 2025; Executive Order 14428, 91 FR 59975; EPA, key developments in the Bay watershed; EPA, evaluation of Pennsylvania’s 2024–2025 milestones.

Method. The end of the milestone period is derived from the period’s name on EPA’s page. EPA’s state evaluations give 2028 for Phase 7; a Bay Program page gives 2027.

Limitations (8)

  • Unverified. Whether EPA will take any backstop action under the TMDL for the missed 2025 nitrogen and phosphorus targets. The 2025 Assessment describes progress and next steps; no backstop decision was found.
  • Unverified. The effect of Executive Order 14428 on the TMDL or on state stormwater programs. The order does not mention the TMDL, and no EPA notice, guidance or grant condition implementing it was found as of October 12, 2026.
  • Coverage. Water-quality standards attainment for 2022–24. It had not been published as of October 12, 2026.
  • Coverage. The values in EPA’s graphic of remaining nitrogen reductions by jurisdiction and sector; it is an image. The shortfalls in Exhibit 4 are computed from the workbook instead.
  • Coverage. Annual watershed-deposition terms for 2010–2023, which the workbook does not publish, so no consistent annual total-load series is drawn for those years.
  • Unverified. The 2033 midpoint check-in reported by Maryland; it is not in the Agreement text.
  • Unverified. A total cost to close the nitrogen gap. No current estimate was found; the Scientific and Technical Advisory Committee’s 2023 figures rest on 2021 model conditions.
  • Coverage. Enacted EPA Bay Program levels for fiscal 2008, 2009, 2011 and 2013–2015, and the fiscal 2027 enacted level.

Sources (8)

  1. EPA: 2025 Assessment of the Chesapeake Bay Program Partnership’s Progress toward the 2025 Water Quality Goal. August 13, 2026; FY 2027 Congressional Justification, Tab 04: Environmental Programs and Management. June 2026; FY 2026 Budget in Brief. May 2025; FY 2017 Budget in Brief; FY 2018 Budget in Brief; FY 2019 Budget in Brief; FY 2020 Budget in Brief; FY 2021 Budget in Brief; FY 2022 Budget in Brief; FY 2023 Budget in Brief; FY 2024 Budget in Brief; FY 2025 Budget in Brief; Budget documents for FY2010–FY2015 in the National Service Center for Environmental Publications (P10069PG); NSCEP record P100DRB5; NSCEP record P100A5RE; NSCEP record P100GCS2; NSCEP record P100I1TE; Chesapeake Bay TMDL, executive summary. December 29, 2010; Key developments in the Chesapeake Bay watershed; Final evaluation of Pennsylvania’s 2024–2025 milestone progress and 2026–2027 milestones. 2026
  2. Chesapeake Bay Program: Chesapeake Bay watershed jurisdictions continue working toward nitrogen and phosphorus goals, with sediment goal already achieved. Press release, August 6, 2026; 2025 Modeled Load Reduction Indicator, data workbook (June 24, 2026); Chesapeake Bay Program model estimates lower amount of nitrogen, phosphorus and sediment pollution entering Chesapeake Bay. Press release, June 3, 2025; Bay jurisdictions continue to chip away at pollution. Blog post, May 2, 2024; Chesapeake Bay water quality shows mixed results. Press release, September 3, 2025; Bay Barometer 2024–2025. March 4, 2026
  3. Chesapeake Bay Program, earlier releases and the model: Phase 6 watershed model (CAST) annual progress scenarios, 1985–2025, as compiled in the 2025 Modeled Load Reduction Indicator workbook; Progress release on the 2015 model run; Progress release on the 2016 model run; Progress release on the 2019 model run; Progress release on the 2020 model run; Progress release on the 2021 model run; Progress release on the 2022 model run; Progress release on the 2023 model run; Water-quality release on 2013–15; Water-quality release on 2015–17; Water-quality release on 2016–18; Water-quality release on 2018–20; Water-quality release on 2020–22
  4. U.S. Geological Survey: Chesapeake Bay River Input Monitoring, annual loads table, water years 1985–2025
  5. Chesapeake Bay Program Scientific and Technical Advisory Committee: Achieving Water Quality Goals in the Chesapeake Bay: A Comprehensive Evaluation of System Response. May 2023
  6. Chesapeake Executive Council: Chesapeake Bay Watershed Agreement, as amended December 2, 2025
  7. Maryland Department of Natural Resources: Release on the Executive Council’s approval of the revised Watershed Agreement. December 2, 2025
  8. Executive Order 14428, Providing Meaningful Water Quality Improvements Through Collaboration and Oversight of Federal Support. 91 FR 59975, September 21, 2026

Read next

  • Pipes and Tunnels The Anacostia tunnels opened in March 2018 and the Northeast Boundary Tunnel in September 2023; the Potomac River Tunnel is due February 8, 2030
  • The Chesapeake and the Region’s Waters In the 2025 model run the watershed had made 57% of the required nitrogen reduction, 90% of the phosphorus and 100% of the sediment

Updated November 12, 2026 · Data as of October 17, 2026.

Data for every exhibit: download (CSV)

The Chesapeake and the Region’s Waters, part 1 of 10.

Next: Study XXI, Pipes and Tunnels