The Capital Region
Conowingo Dam and the Dredging Islands
Conowingo Dam no longer traps the Susquehanna’s sediment, and Bay channel spoil needs new islands: what each fix has bought so far, and at what cost.
12 min read · 14 exhibits
Contracts under the plan to offset Conowingo Dam’s extra nitrogen add to 256,692 pounds a year, 4.28% of the 6.0 million-pound goal. That figure, from the Chesapeake Bay Program’s May 2026 workbook, is the clearest measure of where the first of two physical problems in the Bay cleanup stands. At the head of the Bay, the reservoir behind Conowingo Dam on the Susquehanna has stopped trapping sediment and the nutrients attached to it over the long run. In the middle of the Bay, the shipping channels to Baltimore are dredged every year, and Maryland has for three decades put the material into islands built or rebuilt from it.
This study sets out what each answer has bought so far, in pounds, tons, acres and dollars. Maryland is the center of both. Pennsylvania matters upstream because most of the nitrogen reduction is assigned to it, and Virginia runs the Bay’s other large placement site, Craney Island, on a different cost-sharing model. Contracted, modeled and monitored figures are kept apart and labeled. Where sources define a figure differently, each definition is stated.
The nitrogen the dam lets through
The plan’s goal is 6.0 million pounds of nitrogen a year, the extra load the Bay Program’s models attribute to a reservoir that no longer traps on net. Four other figures go by much the same name. The jurisdictions’ assignments in the Conowingo Watershed Implementation Plan add to 6.67 million pounds. EPA asked for 25%, 1.675 million pounds, by the end of 2025. EPA’s April 2026 evaluation counts 245,300 pounds in the first three milestone commitments, 14.6% of that 25%. The contracts total 256,692.
None of it had been entered in EPA’s reporting system by the June 30, 2025 deadline, and EPA’s 2025 assessment, on its modeled accounting, credits the plan with 3% of its nitrogen target, 1% of phosphorus and 0% of sediment. EPA wrote in April 2026 that the commitments “do not provide confidence that the 25 percent reduction goals will be achieved soon.” The plan is a partnership commitment, not a permit or a decree.
109. Conowingo plan contracts cover 256,692 pounds of nitrogen a year, 4.28% of the 6.0 million-pound goal and 15% of the 1.675 million pounds EPA expected by the end of 2025
Source. Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026); Conowingo Watershed Implementation Plan (2021); EPA evaluation of 2026–2027 milestone commitments (April 15, 2026); CWIP 2022–2025 progress report (January 2026).
Method. The 6.0 million-pound goal and the 6.67 million-pound assignments are modeled loads; the contracted figure is annual pounds promised in contracts, including projects still in design, not reductions verified or credited. EPA’s 25% expectation is 25% of 6.7 million pounds.
Source. Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026); Conowingo Watershed Implementation Plan (2021), assignment table; Maryland Department of the Environment, Conowingo WIP page.
Method. Share under contract: each state’s contracted pounds a year in the workbook divided by its assignment in the plan’s table.
The split matters more than the total. Pennsylvania carries 6.41 million of the 6.67 million pounds because most of the Susquehanna’s farmland lies there; its procurement program has 89,685 pounds under contract. Maryland, assigned 180,000 pounds, has 164,550 under contract, but 157,179 of those sit in two four-year precision nutrient management contracts marked “Year 1 complete.” Across the three states, projects marked implementation complete hold 63,603 pounds, 24.8% of the contracted total (the eight such contracts in Exhibit 111, summed, over 256,692).
Price per pound varies about 25-fold inside one program. Annualized over contract terms, Rosetree Consulting’s Maryland nutrient-management contract costs $5.86 a pound and HGS’s York County wetland and stream restoration $149.34. The workbook average is $12.72, against the $8 a pound assumed for the plan’s primary strategy, which was costed at $53.3 million a year. Short contracts for fertilizer practices are cheap per pound but expire; 20-year wetland and buffer contracts cost more per pound and persist, so a pound a year from one is not the same asset as a pound a year from the other.
111. Annualized contract prices run from $5.86 to $149.34 per pound of nitrogen; the program average, $12.72, is above the $8 the plan assumed
Source. Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026), Detail sheet; Conowingo Watershed Implementation Plan (2021), cost table.
Method. Contract cost divided by contract term, divided by annual pounds, as the workbook computes it. Terms run 4 to 20 years. Chester County’s $3.5 million local-government award states no pounds and is left out. The program average includes Maryland’s $1.875 million administrative charge. The two reference bars are not rows of the table: the $8 is the plan’s cost table, and the $12.72 average is $3.266 million a year annualized (Exhibit 117) over 256,692 pounds a year (Exhibit 110).
Maryland’s own numbers do not yet agree. The Susquehanna River Basin Commission, which administers Maryland’s pay-for-success awards, describes each first-round project by lifetime pounds and lifespan; dividing one by the other gives 46,088 pounds a year. The Bay Program workbook counts 164,550. The gap sits in two entries. HGS’s nutrient-management contract has a 20-year lifespan on the commission’s page and a four-year term in the workbook; Rosetree’s is 123,300 pounds over four years for $772,485 on the page but 123,291 pounds a year for $2.89 million in the workbook. The commission’s page now also lists five 2025 second-round awards, $11.8 million for an estimated 712,547 pounds over lifespans of three to 20 years, which the May 2026 workbook does not include.
112. For Maryland’s five first-round awards, the commission’s figures imply 46,088 pounds of nitrogen a year; the Bay Program workbook counts 164,550
Source. Susquehanna River Basin Commission, Conowingo WIP pay-for-success awardees (2024); Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026).
Method. Commission figures are each project’s estimated lifetime pounds divided by its stated lifespan. Workbook figures are its per-year column. Both are contracted estimates, not verified reductions. Left out of the drawing and kept in the table: the total row.
Why the reservoir matters
Conowingo’s reservoir filled with sediment over most of the twentieth century. The Corps of Engineers’ 2015 assessment of the lower Susquehanna concluded that it, like the two reservoirs above it, had reached a “dynamic equilibrium”: sediment and nutrients still settle between storms, but floods scour the bed, so over the long run the reservoir no longer traps on net. USGS monitoring below the dam shows the result. Flow-normalized nitrogen, a statistical estimate that removes year-to-year swings in river flow, fell 33% from water year 1985 to 2025 as upstream practices took hold. Flow-normalized phosphorus ended 2.6% below where it started, after a peak in 2012, and flow-normalized sediment ended 22% higher, after a peak in 2008.
113. Below the dam, flow-normalized nitrogen fell 33% between water years 1985 and 2025; phosphorus ended near its start and sediment 22% higher, after peaking in 2008
Method. Flow-normalized (statistical estimate): USGS WRTDS estimates built from monitoring samples with year-to-year flow variation removed; they are not observed loads. In 1985 the three series were 167 million pounds of nitrogen, 5.71 million pounds of phosphorus and 1.18 million short tons of sediment; in 2025, 112 million, 5.56 million and 1.44 million.
Year to year, the load arrives in pulses. In USGS’s monitoring-based annual estimates, three water years with major floods, 2011 (Tropical Storm Lee), 2004 and 1996, carried 46% of the suspended sediment that passed the dam in the 41 years from 1985 and 25% of the phosphorus, but 14% of the nitrogen. Sediment and phosphorus move with storms; nitrogen moves with ordinary flow, which is why the cleanup plan buys nitrogen reductions on farms rather than work at the reservoir.
114. Three flood years, 2011, 2004 and 1996, carried 46% of the sediment that passed Conowingo Dam in the 41 water years from 1985 to 2025
Method. Annual loads are USGS WRTDS-Kalman estimates built on monitoring samples, so they include storm-year variability; shares are this study’s arithmetic on the USGS table. A water year runs October through September.
The Corps’ two-dimensional model shows the mechanism. Run the same 2008–11 flows, including Tropical Storm Lee, over the reservoir bed as surveyed in 1996, 2008 and 2011: scour from the bed rises from 1.8 million to 3.0 million tons and net deposition falls from 6.0 million to 4.0 million. How much room is left depends on the definition. USGS estimated about 30 million tons of remaining storage on 2008 bathymetry, 15 to 20 years of filling; the Corps put the lower reservoir about 7 million tons from full on 2011 bathymetry. No bathymetric survey after 2011 was found.
115. In the Corps’ model, the same 2008–11 floods scour 3.0 million tons from the 2011 reservoir bed against 1.8 million from the 1996 bed, and leave 4.0 million tons behind instead of 6.0 million
Source. U.S. Army Corps of Engineers and Maryland Department of the Environment, Lower Susquehanna River Watershed Assessment, final report (2015), Table 4-4.
Method. Modeled: AdH two-dimensional sediment model, million short tons over a four-year simulation of 2008–11 flows. The “full” condition adds 6.2 million tons to the 2011 bed. Total outflow past the dam in the same runs was 20.3, 21.9, 22.3 and 22.2 million tons.
The license and the money
The dam’s federal license expired in 2014. FERC issued a new one in March 2021 on the strength of a 2019 settlement in which Maryland waived its 2018 water quality certification; that certification, as read from the scanned document, required reductions of 6.0 million pounds of nitrogen and 260,000 pounds of phosphorus a year from 2025, or an in-lieu fee. The D.C. Circuit vacated the license on December 20, 2022, holding that FERC had exceeded its authority under section 401 of the Clean Water Act. Maryland issued a revised certification with conditions on October 2, 2025, with a companion settlement among the state, Constellation and two Waterkeeper groups. It has been filed with FERC; state officials expect a decision in 2027 (Maryland Matters, August 14, 2026), and payments begin only after a license issues.
The state announced the agreement as worth more than $340 million over 50 years. Its six itemized lines add to $244.8 million, and the announcement does not explain the $95.2 million difference. The payment schedules in the certification and settlement, as read from scanned tables, add to less again for the lines they cover: $15.9 million for the mussel program against $23.3 million announced, and a $16.4 million dredging reserve against $18.7 million. The revised certification sets no numeric nitrogen or phosphorus requirement. The fish-passage money addresses a steep decline: by the U.S. Fish and Wildlife Service’s counts, American shad collected at the Conowingo fish lift fell from 193,574 in 2001 to 2,051 in 2025, and since 2021 they have been trucked upstream rather than passed through fishways.
116. Maryland’s 2025 Conowingo agreement was announced at more than $340 million over 50 years; its six itemized lines add to $244.8 million
Source. Maryland Department of the Environment, Conowingo Dam agreement announcement (October 2, 2025); revised certification 17-WQC-02(R1).
Method. Values as announced; fish and eel passage is “more than $28 million.” The sum is this study’s arithmetic. The announcement gives no price year or schedule; the certification’s payment tables are CPI-adjusted and begin after a federal license issues. Left out of the drawing and kept in the table: the three scheduled-payment rows read from the certification and settlement.
Dredging the reservoir is the obvious engineering answer and the expensive one. The Corps’ 2015 assessment priced dredging at $16 to $89 a cubic yard, or $48 million to $267 million a year to remove 3 million cubic yards, slightly more than settles behind the dams in an average year. A Maryland pilot dredged about 1,000 cubic yards in 2021 after bids for 25,000 were judged uneconomic, the Maryland Department of the Environment reports. Against that, the settlement’s dredging line is $18.7 million over its term, for studies. The nutrient contracts cost $3.3 million a year annualized, and the plan’s primary strategy was costed at $53.3 million a year. The Corps and Maryland’s reservoir modeling study, due in December 2027 under the plan’s milestones, is meant to settle whether dredging can be credited at all.
117. Dredging the reservoir’s yearly inflow would cost $48 million to $267 million a year in the Corps’ 2015 estimate; the settlement holds $18.7 million in total for dredging studies
Source. Lower Susquehanna River Watershed Assessment (2015); Maryland certification 17-WQC-02 (2018); Conowingo Watershed Implementation Plan (2021); Conowingo WIP Reductions Summary (May 2026); Maryland Department of the Environment (October 2, 2025).
Method. The 2018 figure is this study’s arithmetic on the certification’s in-lieu fees, $17 a pound of nitrogen and $270 a pound of phosphorus in 2019 dollars, read from a scanned document; it never took effect. The Corps gives no price year for its range. The settlement line is a total over the term, not an annual amount.
The islands
The second problem is where to put what the shipping channels give up. Maryland’s answer has been containment: Hart-Miller Island, closed to placement in 2009; Cox Creek and Masonville in Baltimore Harbor; Poplar Island off Talbot County for material from the Bay channels; and next, the Mid-Chesapeake Bay Island project at James and Barren Islands in Dorchester County. The Maryland Port Administration reports enough remaining capacity for 20 years of projected dredging in all four channel segments as of June 2025, with the thinnest margins in the C&D Canal approaches, 12.4 million cubic yards of need against 14.8 million of capacity, and Baltimore Harbor: 23.1 million cubic yards of need against 28.6 to 30.4 million of capacity. That capacity counts projects not yet built, and the port’s 2022 annual report showed the harbor with a deficit of 0.3 million cubic yards in June 2022.
118. Maryland’s port reports placement capacity above 20 years of dredging need in all four channel segments; the C&D Canal approaches and Baltimore Harbor have the narrowest margins
Source. Maryland Port Administration, Dredged Material Management Program annual report (2025), 20-year capacity table as of June 30, 2025.
Method. Million cubic yards. Need is the port’s 20-year planning projection (modeled); capacity is as reported and includes sites not yet complete (Cox Creek and Masonville raisings, Mid-Bay, innovative reuse). Each segment is drawn on its own scale; the report gives more than 100 million cubic yards for the Maryland Bay approaches and more than 1,000 million for the Virginia approaches, drawn at those floors. Baltimore Harbor capacity is a range; the bar shows its low end. Margin: capacity less need, 2.4 million cubic yards for the C&D Canal approaches (14.8 less 12.4) and 5.5 to 7.3 million for Baltimore Harbor.
Poplar Island carries most Bay-channel material until Mid-Bay opens. The state estimates about 47 million cubic yards placed by October 2025, 66% of a stated 71.1 million, leaving 24 million. The capacity itself has been restated, from 39.5 million in the original design to about 68, 70, 71 and 71.1 million across documents, and the last year of placement is given as 2029 on the Corps’ page, 2032 in a 2021 release, and the 2032/33 or 2033/34 dredging cycle in state reports. Filling 24 million cubic yards before the 2032/33 cycle would take about 3.4 million a season (24 million over the seven seasons from 2025/26 to 2031/32, derived); the port’s 2025 annual report records 1.9 million received in early 2025.
119. Poplar Island, the main site for Bay-channel material, is nearing capacity, and its documents disagree on how large it is and when it closes
Source. Maryland Port Administration, Dredged Material Management Program annual reports (2022, 2024, 2025); Poplar Island site page; U.S. Army Corps of Engineers Baltimore District, Poplar Island page.
Method. Placed volumes are the state’s estimates. Remaining capacity was reported as 24 million cubic yards in December 2023 (on an unstated base of about 68.6 million), 26 million in April 2024 and 24 million in October 2025. The Corps’ page carries no date.
The islands are also habitat projects, and their habitat is mostly a design target. Poplar Island is to finish at 1,715 acres, about 776 of them wetland, by 2041. Mid-Bay is to restore 2,144 acres by 2067: James Island’s 2,072, split 55% wetland and 45% upland, and Barren Island’s 72 acres of wetland. No source reports wetland acres built to date at either. The built figures are smaller: more than 46 or more than 50 acres of restored wetland at Masonville Cove, depending on the document, and 126 acres of existing wetland preserved at Cox Creek.
120. Mid-Bay is designed to restore 2,144 acres of island habitat by 2067; no source reports wetland acres built to date at Poplar Island or Mid-Bay
Source. Maryland Board of Public Works, July 6, 2022 agenda, item 3-GM (Mid-Bay); U.S. Army Corps of Engineers Baltimore District (April 2026); Corps Poplar Island page; Masonville, Cox Creek and Hart-Miller Island site pages.
Method. Masonville Cove is “over 50 acres of restored wetlands” on the site page and “over 46 acres of restored wetlands, uplands, and nature trails” in a November 2024 fact sheet; the bar shows 50. Hart-Miller’s 1,100 acres are the whole island; its wetland acres are not stated.
Who pays, in Maryland and Virginia
Mid-Bay’s 2022 partnership agreement puts the project at $4.60 billion: 65% federal and 35%, $1.61 billion, from the Maryland Port Administration, of which $1.03 billion is for Maryland Environmental Service operations, monitoring and habitat work. In USAspending’s award records, the Corps has obligated $201.6 million on 4 Mid-Bay contracts since 2009, 4.4% of the total: two Barren Island phases by Coastal Design & Construction and Seacoast Construction, a 2009 breakwater, and the first James Island phase by C&C Joint Ventures, $111.4 million obligated of $122.2 million with options. The state’s reports count $155.8 million of federal funding to date as of November 2025, a different measure.
At Poplar, federal obligations visible in USAspending since fiscal 2008 total $165.6 million across 19 contracts, against a $1.4 billion estimate on the Corps’ page that gives no price year; the project dates to a 1996 decision, before USAspending’s coverage begins. Maryland’s Cox Creek expansion runs through a state interagency agreement with Maryland Environmental Service whose not-to-exceed ceiling has risen from $116.0 million to $212.0 million over three modifications (Board of Public Works, May 21, 2025); that is authority, not spending.
Virginia’s model is different. Craney Island in Portsmouth is a federal placement area that the Virginia Port Authority is expanding eastward for a marine terminal. The 2006 Chief’s Report put the 580-acre expansion at $671.3 million in October 2005 prices, 96% non-federal; the 2012 partnership agreement gives $1.062 billion for 522 acres, 49.1% non-federal, at an unstated price level, so the two are not like-for-like. In USAspending’s records, Corps contracts at Craney total $147.8 million in obligations since fiscal 2008, the largest Norfolk Dredging’s phase 1C new-work dredging. The 2006 plan expected the first terminal phase in operation by 2017; no current status was found.
121. The Corps has obligated $201.6 million on Mid-Bay contracts, 4.4% of the $4.60 billion in the 2022 partnership agreement
Source. Maryland Board of Public Works, July 6, 2022 agenda, item 3-GM; May 21, 2025 agenda (Cox Creek); USAspending.gov award records (October 2026); Corps Poplar Island page; Craney Island partnership agreement (2012).
Method. Obligations are net federal obligations on Corps prime contracts as of October 2026, from fiscal 2008 on; they are not payments and exclude the state’s share. Mid-Bay and Craney are agreement totals; Poplar is the Corps’ undated estimate with no price year; Cox Creek is a not-to-exceed ceiling on a state interagency agreement.
What comes next
The next three years settle the dam’s question more than the islands’. A FERC license decision, which state officials expect in 2027 (Maryland Matters), starts the settlement’s payments. The reservoir modeling study and the plan’s 2026–27 milestones are due in December 2027; those milestones, 77,200 pounds for Pennsylvania, 164,550 for Maryland and 2,500 for New York, together equal 3.7% of the 6.67 million-pound assignment. For the islands, Barren Island is to take its first Honga River material in fall 2026, Cox Creek’s next dike raising is projected for 2028 to 2030, and James Island is to accept material around 2030, close to when Poplar Island fills.
122. James Island is due to take dredged material around 2030, as Poplar Island closes, and Mid-Bay is to be complete in 2067
Source. U.S. Army Corps of Engineers Baltimore District (April 2026); Conowingo WIP 2026–2027 milestone commitments; Maryland Matters (August 14, 2026); Dredged Material Management Program reports (2022–2026); Corps Poplar Island page; AJOT (January 2021).
Method. Filled dot: a dated commitment in a milestone document. Open dots: projected or expected dates and windows, which are not binding. The modeling study’s completion is June 2027 in a press report and December 2027 in the plan’s milestones; Poplar’s last placement is 2029, 2032, the 2032/33 or the 2033/34 cycle depending on the source.
Limitations (9)
- Unverified. Poplar Island volumes and Maryland’s capacity-versus-need table. The port’s 2025 annual report, reopened for this page, gives the June 30, 2025 table, Poplar’s 47 million cubic yards placed and 24 million remaining as of October 2025, and the 1.9 million received in early 2025; its 2022 report gives the harbor’s June 2022 deficit. Poplar’s other stated capacities and remaining figures come from the reports as recorded in earlier research and were not re-read, and Poplar’s placed volumes are themselves estimates.
- Unverified. The dam’s license status in 2026. No FERC order after the October 2025 certification was found; the 2027 decision date is a press report of state officials’ expectation.
- Unverified. The settlement’s payment schedules, which were read by optical character recognition from scanned tables, and the $95.2 million gap between the announced $340 million and the itemized lines, which no document explains.
- Conflicting sources. Why the commission’s page and the Bay Program workbook differ for HGS and Rosetree, and the size of Maryland’s fund: $25 million on the state’s page, “over $20 million” in the commission’s program document; the state says seven first-round projects, the commission lists five awards.
- Conflicting sources. Remaining reservoir storage, which depends on definition (about 30 million tons in USGS’s 2008 estimate, about 7 million tons to full in the lower reservoir in the Corps’ 2015 assessment), and the volume of sediment in the reservoir, 200 million or 253 million cubic yards in two state reports. No survey after 2011 was found.
- Conflicting sources. Wetland acres built to date at Poplar Island and Mid-Bay; Masonville Cove’s 46 versus 50 acres; whether Masonville’s next raising adds about 4 million or 2.2 million cubic yards and Cox Creek’s about 6.2 million or 6.5 million; volumes placed at Cox Creek and Masonville, which are not reported.
- Unverified. Mid-Bay’s total cost outside the 2022 partnership agreement, which no Corps or state report restates; Poplar Island’s $1.4 billion has no price year; Craney Island’s 2006 and 2012 costs are on different price levels and acreages, and its current status, like Hampton Roads’ beneficial-use project after 2024, was not found.
- Coverage. Federal obligations before fiscal 2008 and subcontracts, which USAspending does not cover; obligations are not payments.
- Unverified. Where the dredged material from the 2024 Key Bridge channel clearance went, beyond the state’s statement that none went to its containment sites.
Sources (13)
- Chesapeake Bay Program: Conowingo Watershed Implementation Plan nutrient reduction and pay-for-performance contracts (Reductions Summary workbook), update date May 11, 2026; Conowingo Watershed Implementation Plan, final, July 2021 (revised); Conowingo WIP 2026–2027 milestone commitments; Conowingo WIP 2022–2025 milestone progress report (January 15, 2026)
- U.S. Environmental Protection Agency: Evaluation of the Conowingo WIP 2026–2027 draft milestone commitments (April 15, 2026); 2025 Assessment of Chesapeake Bay Program partnership progress toward the 2025 water quality goal (August 13, 2026)
- Maryland Department of the Environment: Conowingo Watershed Implementation Plan; Conowingo Dam water quality certification, revised certification 17-WQC-02(R1) (October 2, 2025); 2025 Conowingo Dam Water Quality Settlement Agreement; Water quality certification 17-WQC-02 (April 27, 2018); “Governor Moore announces historic Conowingo Dam agreement” (October 2, 2025); Conowingo Dam impacts and dredging pilot; Conowingo innovative reuse and beneficial use report (December 5, 2022)
- Susquehanna River Basin Commission: Conowingo Watershed Implementation Plan: pay-for-success awardees, 2024 and 2025
- U.S. Geological Survey: Chesapeake Bay River Input Monitoring annual loads table, water years 1985–2025; Langland, M. J., Bathymetry and sediment-storage capacity change in three reservoirs on the lower Susquehanna River, 1996–2008 (Scientific Investigations Report 2009-5110)
- U.S. Army Corps of Engineers: Lower Susquehanna River Watershed Assessment, Maryland and Pennsylvania, final report, with the Maryland Department of the Environment (May 2015); Baltimore District, Paul S. Sarbanes Ecosystem Restoration Project at Poplar Island; Baltimore District, “U.S. Army Corps of Engineers awards $53 million contract for Mid-Chesapeake Bay Island project” (April 2026); Report of the Chief of Engineers, Craney Island Eastward Expansion, Norfolk Harbor and Channels, Virginia (October 24, 2006); Norfolk District and Virginia Port Authority, Project Partnership Agreement, Craney Island Eastward Expansion (June 2012)
- U.S. Court of Appeals for the D.C. Circuit: Waterkeepers Chesapeake v. FERC, No. 21-1139 (decided December 20, 2022)
- U.S. Fish and Wildlife Service: Susquehanna River fish passage, annual American shad counts at Conowingo Dam
- Maryland Port Administration: Dredged Material Management Program annual report, 2022; Dredged Material Management Program annual report, 2025; Dredged Material Management Program mid-year report, 2026; Poplar Island; Masonville; Cox Creek; Hart-Miller Island
- Maryland Board of Public Works: Department of Transportation action agenda, July 6, 2022, item 3-GM (Mid-Bay Project Partnership Agreement); Department of Transportation action agenda, May 21, 2025 (Cox Creek Expanded DMCF, Modification 3)
- USAspending.gov: Prime award records, U.S. Army Corps of Engineers contracts at Poplar Island, Barren and James Islands and Craney Island, fiscal 2008–2026
- Maryland Matters: Conowingo county advisory group (August 14, 2026)
- American Journal of Transportation: Poplar Island construction complete, planning for Mid-Bay (January 20, 2021)
Read next
- The Cleanup Shortfall and Coming Deadlines
- The Chesapeake and the Region’s Waters In the 2025 model run the watershed had made 57% of the required nitrogen reduction, 90% of the phosphorus and 100% of the sediment
A principal of Higgins Strategy is employed by a contractor in the regional stormwater market. No figure in this study was obtained through that employment, and no company was added to or removed from the data on that account.
The Chesapeake and the Region’s Waters, part 9 of 10.