From Study XXI, Exhibit 13

The Anacostia tunnels opened in March 2018 and the Northeast Boundary Tunnel in September 2023; the Potomac River Tunnel is due February 8, 2030

Source. DC Water Board resolutions; HRSD Commission minutes; Baltimore Board of Estimates minutes; Virginia DEQ report RD662; DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond report RD1001 (2024); Philadelphia Year 10 plan; ALCOSAN 2026 budget.

Method. Bars run from contract award (or decree, order or plan year where no single contract governs) to the in-service date or, where work is unfinished, to the legal deadline (black tick) or the owner’s projected date (open circle); the James River SWIFT bar stops at October 2026 because no completion date was found. Values are the approved contract figure, HRSD’s stipulated price, or the owner’s program estimate where no single contract covers the work. Joint-venture values are whole-contract. Patapsco and Back River in-service dates are Maryland’s BayStat dates and may be year placeholders.

ProjectGroupStatus, October 2026Value ($)Detail
Blue Plains TunnelDistrict of Columbiain service330,561,000Awarded 2011, in operation 2018 · $330.6M awarded, $318.7M final · Traylor/Skanska/Jay Dee JV
Anacostia River TunnelDistrict of Columbiain service253,859,999Awarded 2013, in operation March 2018 · $253.9M · Impregilo-Healy-Parsons JV
Blue Plains enhanced nitrogen removalDistrict of Columbiain service69,502,000Design 2009 (CH2M Hill), online 2015 · tankage $69.5M · PC Construction
Northeast Boundary TunnelDistrict of Columbiain service579,975,000Awarded 2017, in operation Sept 2023 (due March 2025) · $580.0M · Salini Impregilo-Healy JV
Potomac River TunnelDistrict of Columbialegal deadline ahead819,655,177Awarded Oct 2023, due in operation Feb 8, 2030 · $819.7M not-to-exceed · CBNA-Halmar JV
Rock Creek storage (Piney Branch Tunnel)District of Columbialegal deadline aheadAwarded Aug 2025, due in operation Nov 2029 · contract value and builder not found
Baltimore · Patapsco nutrient-removal filtersMarylandin service245,438,000Awarded 2009 and 2012, in service 2020 · $245.4M in two contracts · Fru-Con
Baltimore · Back River nutrient removal (SC 877)Marylandin service263,500,000Approved Aug 2013, in service Sept 2017 · $263.5M · Archer Western
Baltimore · sewer overflow consent decreeMarylandlegal deadline ahead1,036,000,000Decree 2002, modified 2017; Phase II due 2030, 2046 proposed · Phase I cost $1,036.0M
Alexandria · RiverRenew tunnelVirginiain service454,400,000Awarded Nov 2020, online July 2026 · $454.4M · Traylor-Shea JV
HRSD · James River SWIFT and nutrient upgradeVirginiaunder way, no completion date found534,098,839Price set May 2022; 83.7% complete June 2025 · $534.1M · Ulliman Schutte-Alberici JV
HRSD · Nansemond SWIFT and recharge wellsVirginiaprojected completion ahead608,717,209Builder chosen Aug 2024; completion projected mid-2028 · $608.7M + $85.9M wells · Garney
Richmond · combined sewer overflow planVirginialegal deadline ahead575,000,000Interim projects due July 1, 2027, final plan July 1, 2035 · $575M estimate (2024)
Lynchburg · Blackwater storage tunnelVirginiaprojected completion ahead103,900,0002015 plan; tunnel mined July 2026, completion projected summer 2027 · $103.9M · Atkinson
Philadelphia · Green City, Clean Waters (Delaware basin)Outside the Bay, for comparisonlegal deadline ahead2,400,000,000Order June 2011; 85% capture due 2036 · $2.40B nominal plan cost (2011)
ALCOSAN, Pittsburgh (Ohio basin)Outside the Bay, for comparisonlegal deadline ahead4,663,545,000Decree entered May 2020; interim measures due 2036 · $4.66B active-program estimate (2026)

Download pipes-and-tunnels-01-project-register.csv

Download SVG · CSV. Data and chart licensed CC BY 4.0.