The Anacostia tunnels opened in March 2018 and the Northeast Boundary Tunnel in September 2023; the Potomac River Tunnel is due February 8, 2030
Source. DC Water Board resolutions; HRSD Commission minutes; Baltimore Board of Estimates minutes; Virginia DEQ report RD662; DC Water consent-decree report, Q2 2026; Baltimore consent-decree report 34 (2026); Richmond report RD1001 (2024); Philadelphia Year 10 plan; ALCOSAN 2026 budget.
Method. Bars run from contract award (or decree, order or plan year where no single contract governs) to the in-service date or, where work is unfinished, to the legal deadline (black tick) or the owner’s projected date (open circle); the James River SWIFT bar stops at October 2026 because no completion date was found. Values are the approved contract figure, HRSD’s stipulated price, or the owner’s program estimate where no single contract covers the work. Joint-venture values are whole-contract. Patapsco and Back River in-service dates are Maryland’s BayStat dates and may be year placeholders.
| Project | Group | Status, October 2026 | Value ($) | Detail |
|---|---|---|---|---|
| Blue Plains Tunnel | District of Columbia | in service | 330,561,000 | Awarded 2011, in operation 2018 · $330.6M awarded, $318.7M final · Traylor/Skanska/Jay Dee JV |
| Anacostia River Tunnel | District of Columbia | in service | 253,859,999 | Awarded 2013, in operation March 2018 · $253.9M · Impregilo-Healy-Parsons JV |
| Blue Plains enhanced nitrogen removal | District of Columbia | in service | 69,502,000 | Design 2009 (CH2M Hill), online 2015 · tankage $69.5M · PC Construction |
| Northeast Boundary Tunnel | District of Columbia | in service | 579,975,000 | Awarded 2017, in operation Sept 2023 (due March 2025) · $580.0M · Salini Impregilo-Healy JV |
| Potomac River Tunnel | District of Columbia | legal deadline ahead | 819,655,177 | Awarded Oct 2023, due in operation Feb 8, 2030 · $819.7M not-to-exceed · CBNA-Halmar JV |
| Rock Creek storage (Piney Branch Tunnel) | District of Columbia | legal deadline ahead | Awarded Aug 2025, due in operation Nov 2029 · contract value and builder not found | |
| Baltimore · Patapsco nutrient-removal filters | Maryland | in service | 245,438,000 | Awarded 2009 and 2012, in service 2020 · $245.4M in two contracts · Fru-Con |
| Baltimore · Back River nutrient removal (SC 877) | Maryland | in service | 263,500,000 | Approved Aug 2013, in service Sept 2017 · $263.5M · Archer Western |
| Baltimore · sewer overflow consent decree | Maryland | legal deadline ahead | 1,036,000,000 | Decree 2002, modified 2017; Phase II due 2030, 2046 proposed · Phase I cost $1,036.0M |
| Alexandria · RiverRenew tunnel | Virginia | in service | 454,400,000 | Awarded Nov 2020, online July 2026 · $454.4M · Traylor-Shea JV |
| HRSD · James River SWIFT and nutrient upgrade | Virginia | under way, no completion date found | 534,098,839 | Price set May 2022; 83.7% complete June 2025 · $534.1M · Ulliman Schutte-Alberici JV |
| HRSD · Nansemond SWIFT and recharge wells | Virginia | projected completion ahead | 608,717,209 | Builder chosen Aug 2024; completion projected mid-2028 · $608.7M + $85.9M wells · Garney |
| Richmond · combined sewer overflow plan | Virginia | legal deadline ahead | 575,000,000 | Interim projects due July 1, 2027, final plan July 1, 2035 · $575M estimate (2024) |
| Lynchburg · Blackwater storage tunnel | Virginia | projected completion ahead | 103,900,000 | 2015 plan; tunnel mined July 2026, completion projected summer 2027 · $103.9M · Atkinson |
| Philadelphia · Green City, Clean Waters (Delaware basin) | Outside the Bay, for comparison | legal deadline ahead | 2,400,000,000 | Order June 2011; 85% capture due 2036 · $2.40B nominal plan cost (2011) |
| ALCOSAN, Pittsburgh (Ohio basin) | Outside the Bay, for comparison | legal deadline ahead | 4,663,545,000 | Decree entered May 2020; interim measures due 2036 · $4.66B active-program estimate (2026) |