From Study XXI, Exhibit 24

Rock Creek Project A cost about $1.17 million per impervious acre managed, 3.9 to 4.7 times the 2015 plan’s 30% scenarios of $249,553 and $298,532 an acre

Source. DC Water, Long Term Control Plan Modification for Green Infrastructure (May 2015), Technical Memorandum 7 and Appendix K; Potomac River Green Infrastructure Practicability Assessment (August 2020), Table 2-8; Rock Creek Project C description (2024).

Method. Built figures are capital cost (design and construction) divided by impervious acres managed, in nominal dollars of the build years; planning figures are construction-cost unit rates on a 2012-dollar basis. The 2024 Rock Creek C figure is the midpoint of a $600,000–$825,000 range.

ItemCost per impervious acre ($)Basis
Planned: Piney Branch budget assumption (2015)165,000budgeted
Planned: Piney Branch 30% scenario (2012 $)249,553budgeted
Planned: Potomac 30% scenario (2012 $)298,532budgeted
Estimate: Rock Creek C alley paving (2024)712,500budgeted
Built: downspout disconnection570,000reported
Built: AlleyPalooza646,500reported
Built: Potomac Project A859,000reported
Built: Kennedy Street1,033,300reported
Built: Challenge Parks1,083,500reported
Built: Rock Creek Project A1,165,200reported