Conowingo plan contracts cover 256,692 pounds of nitrogen a year, 4.28% of the 6.0 million-pound goal and 15% of the 1.675 million pounds EPA expected by the end of 2025
Source. Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026); Conowingo Watershed Implementation Plan (2021); EPA evaluation of 2026–2027 milestone commitments (April 15, 2026); CWIP 2022–2025 progress report (January 2026).
Method. The 6.0 million-pound goal and the 6.67 million-pound assignments are modeled loads; the contracted figure is annual pounds promised in contracts, including projects still in design, not reductions verified or credited. EPA’s 25% expectation is 25% of 6.7 million pounds.
| Measure | Nitrogen (lb a year) | Basis | Source URL |
|---|---|---|---|
| Assignments in the plan (2021) | 6,670,000 | modeled | https://www.chesapeakebay.net/files/documents/final_cwip_2024-06-20-152643_gxnv.pdf |
| Goal: extra load from infill | 6,000,000 | modeled | https://www.chesapeakebay.net/files/documents/final_cwip_2024-06-20-152643_gxnv.pdf |
| EPA: 25% by Dec. 31, 2025 | 1,675,000 | modeled (EPA expectation) | https://www.epa.gov/system/files/documents/2026-04/epa_evaluation_of_conowingo_2026-2027_draft_milestone_commitments.pdf |
| Contracted, May 11, 2026 | 256,691.76 | contracted | https://www.chesapeakebay.net/files/CWIP-Reductions-Summary.xlsx |
| EPA: milestones 1–3 (Apr. 2026) | 245,300 | contracted (EPA count) | https://www.epa.gov/system/files/documents/2026-04/epa_evaluation_of_conowingo_2026-2027_draft_milestone_commitments.pdf |
| Reported to EPA by June 30, 2025 | 0 | reported | https://www.chesapeakebay.net/files/documents/CWIP_22-25progress-report.pdf |