Dredging the reservoir’s yearly inflow would cost $48 million to $267 million a year in the Corps’ 2015 estimate; the settlement holds $18.7 million in total for dredging studies
Source. Lower Susquehanna River Watershed Assessment (2015); Maryland certification 17-WQC-02 (2018); Conowingo Watershed Implementation Plan (2021); Conowingo WIP Reductions Summary (May 2026); Maryland Department of the Environment (October 2, 2025).
Method. The 2018 figure is this study’s arithmetic on the certification’s in-lieu fees, $17 a pound of nitrogen and $270 a pound of phosphorus in 2019 dollars, read from a scanned document; it never took effect. The Corps gives no price year for its range. The settlement line is a total over the term, not an annual amount.
| Item | Low ($ million) | High ($ million) | Period | Basis |
|---|---|---|---|---|
| Dredge 3 million cubic yards a year (LSRWA 2015) | 48 | 267 | per year | modeled |
| 2018 certification in-lieu option, 6.0M lb N x $17 + 0.26M lb P x $270 | 172.2 | 172.2 | per year | derived; never in force |
| Conowingo plan primary strategy | 53.3 | 53.3 | per year | modeled |
| Conowingo plan contracts, annualized (May 2026) | 3.266 | 3.266 | per year | contracted |
| Settlement dredging line | 18.7 | 18.7 | whole term | announced |