The Corps has obligated $201.6 million on Mid-Bay contracts, 4.4% of the $4.60 billion in the 2022 partnership agreement
Source. Maryland Board of Public Works, July 6, 2022 agenda, item 3-GM; May 21, 2025 agenda (Cox Creek); USAspending.gov award records (October 2026); Corps Poplar Island page; Craney Island partnership agreement (2012).
Method. Obligations are net federal obligations on Corps prime contracts as of October 2026, from fiscal 2008 on; they are not payments and exclude the state’s share. Mid-Bay and Craney are agreement totals; Poplar is the Corps’ undated estimate with no price year; Cox Creek is a not-to-exceed ceiling on a state interagency agreement.
| Project | Cost, estimate or ceiling ($ million) | Federal obligations ($ million) | Contracts | Basis |
|---|---|---|---|---|
| Mid-Bay (James and Barren Islands) | 4,596.303 | 201.627 | 4 | agreement total; net obligations |
| Poplar Island | 1,400 | 165.58 | 19 | undated estimate; net obligations FY2008+ |
| Craney Island Eastward Expansion (Virginia) | 1,062.107 | 147.828 | 31 | 2012 agreement total; net obligations FY2008+ |
| Cox Creek Expanded DMCF | 212 | 0 | not-to-exceed ceiling, state interagency agreement |