Annualized contract prices run from $5.86 to $149.34 per pound of nitrogen; the program average, $12.72, is above the $8 the plan assumed
Source. Chesapeake Bay Program, Conowingo WIP Reductions Summary workbook (May 11, 2026), Detail sheet; Conowingo Watershed Implementation Plan (2021), cost table.
Method. Contract cost divided by contract term, divided by annual pounds, as the workbook computes it. Terms run 4 to 20 years. Chester County’s $3.5 million local-government award states no pounds and is left out. The program average includes Maryland’s $1.875 million administrative charge. The two reference bars are not rows of the table: the $8 is the plan’s cost table, and the $12.72 average is $3.266 million a year annualized (Exhibit 117) over 256,692 pounds a year (Exhibit 110).
| Contractor | Project | State | Status | Term (years) | Nitrogen (lb a year) | Contract ($) | Annualized cost ($ per lb of nitrogen) |
|---|---|---|---|---|---|---|---|
| Rosetree Consulting, LLC | Precision Nutrient Management | Maryland | Year 1 complete | 4 | 123,291 | 2,889,941.04 | 5.86 |
| Keystone Streams, LLC | Keystone Streams Rohrer Farm Riparian Forest Buffer | Pennsylvania | Implementation complete | 20 | 748.83 | 98,321.38 | 6.57 |
| Lancaster Farmland Trust | Dairy and Sheep Farm Stormwater Management BMPs (2 sites) | Pennsylvania | Design | 20 | 9,033.3 | 1,248,763.39 | 6.91 |
| Conservation Innovation Fund | Alternative Crops for Environmental Benefits | Pennsylvania | Construction | 20 | 11,767.27 | 1,663,774.31 | 7.07 |
| Chesapeake Conservancy, Inc. | Beef and Poultry Farm BMPs | Pennsylvania | Implementation complete | 20 | 930.32 | 185,338.35 | 9.96 |
| HGS, LLC | Wetland and Riparian Grass Buffers Restoration Conowingo Creek | Pennsylvania | Implementation complete | 20 | 29,438.95 | 5,869,832.24 | 9.97 |
| HGS, LLC | Precision Nutrient Management | Maryland | Year 1 complete | 4 | 33,888.45 | 2,033,307 | 15 |
| Upper Susquehanna Coalition | Natural filters and sustainable farm practices | New York | Planning/Design | 5 | 2,457 | 221,665.75 | 18.04 |
| Alliance for the Chesapeake | Forest Riparian Buffers and Land Use Conversion | Maryland | Planning/Design | 15 | 2,332.9 | 664,175.68 | 18.98 |
| HGS, LLC | Wetland Restoration in Adams County | Pennsylvania | Implementation complete | 20 | 19,617.24 | 7,458,474.65 | 19.01 |
| HGS, LLC | Wetland Restoration and Riparian Buffer Fencing in York County | Pennsylvania | Implementation complete | 20 | 8,651.44 | 4,349,944.03 | 25.14 |
| HGS, LLC | Wetland re-establishment, wetland restoration, pasture fencing, and forested buffers (2 sites) | Pennsylvania | Design | 20 | 6,568.63 | 4,237,883.02 | 32.26 |
| Herbert, Rowland, & Grubic, Inc. | Dairy and Beef Farm BMPs (2 sites) | Pennsylvania | Implementation complete | 20 | 2,703 | 2,195,998.29 | 40.62 |
| Keystone Stream, LLC | Forest Riparian Buffers | Maryland | Implementation complete | 20 | 1,287.13 | 1,274,258 | 49.5 |
| Ecotone, LLC | Stream Restoration (2 Projects) | Maryland | Planning/Design | 10 | 3,750.3 | 4,836,201 | 128.96 |
| HGS, LLC | Wetland and Stream Restoration and Riparian Plantings in York County | Pennsylvania | Implementation complete | 20 | 226 | 675,016.8 | 149.34 |
Download the-dam-and-the-islands-03-unit-cost-by-contract.csv