From Study XXI, Exhibit 118

Maryland’s port reports placement capacity above 20 years of dredging need in all four channel segments; the C&D Canal approaches and Baltimore Harbor have the narrowest margins

Source. Maryland Port Administration, Dredged Material Management Program annual report (2025), 20-year capacity table as of June 30, 2025.

Method. Million cubic yards. Need is the port’s 20-year planning projection (modeled); capacity is as reported and includes sites not yet complete (Cox Creek and Masonville raisings, Mid-Bay, innovative reuse). Each segment is drawn on its own scale; the report gives more than 100 million cubic yards for the Maryland Bay approaches and more than 1,000 million for the Virginia approaches, drawn at those floors. Baltimore Harbor capacity is a range; the bar shows its low end. Margin: capacity less need, 2.4 million cubic yards for the C&D Canal approaches (14.8 less 12.4) and 5.5 to 7.3 million for Baltimore Harbor.

Channel segment20-year need (million cubic yards)Capacity (million cubic yards)Capacity, high (million cubic yards)As ofBasis
Baltimore Harbor23.128.630.42025-06-30need modeled; capacity reported
Maryland Bay approaches401002025-06-30need modeled; capacity reported
Virginia Bay approaches24.81,0002025-06-30need modeled; capacity reported
C&D Canal approaches12.414.82025-06-30need modeled; capacity reported

Download the-dam-and-the-islands-10-capacity-vs-need-2025.csv

Download SVG · CSV. Data and chart licensed CC BY 4.0.