From Study XXI, Exhibit 122

James Island is due to take dredged material around 2030, as Poplar Island closes, and Mid-Bay is to be complete in 2067

Source. U.S. Army Corps of Engineers Baltimore District (April 2026); Conowingo WIP 2026–2027 milestone commitments; Maryland Matters (August 14, 2026); Dredged Material Management Program reports (2022–2026); Corps Poplar Island page; AJOT (January 2021).

Method. Filled dot: a dated commitment in a milestone document. Open dots: projected or expected dates and windows, which are not binding. The modeling study’s completion is June 2027 in a press report and December 2027 in the plan’s milestones; Poplar’s last placement is 2029, 2032, the 2032/33 or the 2033/34 cycle depending on the source.

ItemDateType
Barren Island: first dredged materialfall 2026projected or expected
FERC license decision (state expectation)2027projected or expected
Reservoir modeling study completeJune or Dec. 2027projected or expected
Conowingo plan milestones 1–3 dueDec. 2027milestone
Cox Creek +80-ft dike raising, construction2028–2030projected or expected
Poplar Island: last placement2029 to 2033/34projected or expected
James Island: accepts dredged materialaround 2030projected or expected
Poplar Island: habitat complete2041projected or expected
Mid-Bay complete2067projected or expected