The Bay cleanup is, in the end, a purchase of pounds: pounds of nitrogen, phosphorus and sediment kept out of the water, bought with public money. Bioretention is one way to buy them. This part prices it, using Maryland’s own project records, sets the price beside the alternatives, and follows the cost past construction into the decades of upkeep that decide whether a cell goes on removing anything at all.
The price of a pound
In 2021 the University of Maryland Center for Environmental Science priced every stormwater and farm practice in the state’s cleanup plan on the same basis: reported project costs, annualized over the practice’s life at 5 percent, divided by the pounds the Bay model credits it with removing at the edge of tidal water, in 2017 dollars. For bioretention on clay soils with an underdrain, the design most of the region’s suburbs require, the median was $6,226 per pound of nitrogen and $40,665 per pound of phosphorus, from 17 projects. On sandy soils the same practice cost $1,558 a pound of nitrogen, a quarter as much. A sand filter removed a pound for $384, a wet pond for $1,845, a planted acre of forest for $605. The median farm practice did it for $16.
15. Annualized cost per pound of nitrogen removed, Maryland practices
Source. Price, Flemming and Wainger, Cost Analysis of Stormwater and Agricultural Practices for Reducing Nitrogen and Phosphorus Runoff in Maryland, UMCES TS-772-21 (March 2021).
Method. Median project costs annualized at 5 percent over each practice’s assumed life (20 years for bioretention), with operation and maintenance added, divided by CAST-credited pounds delivered to tidal water. Bioswale (1 project), sweeping (2) and permeable pavement (2) rest on fewer than three projects. Costs are measured; the pounds are modeled credits.
16. Annualized cost per pound of phosphorus removed, Maryland practices
Source. UMCES TS-772-21 (March 2021).
Method. Same method as Exhibit 15. The phosphorus credit for bioretention assumes the cell removes phosphorus; Part 2 shows that measured phosphorus concentrations leaving conventional cells are higher than those entering, so the modeled pounds, and therefore the price per pound, are uncertain in both directions.
Two things drive the ranking. One is the credit: a clay-soil cell is credited with 2.08 pounds of nitrogen a year per acre treated, a sandy-soil cell with 5.83, a sand filter with 3.33. The other is the capital cost per acre, which is where bioretention is dearest. The practice was invented to fit onto lots and into parking islands, and small, dispersed, planted things cost more to build per acre than one large basin at the bottom of a hill.
17. Planning-level construction cost per impervious acre, Maryland, 2011
Source. King and Hagan, Costs of Stormwater Management Practices in Maryland Counties, UMCES TS-626-11, report to MDE (October 2011).
Method. Planning-level averages in 2011 dollars, including land at $50,000 an acre; not adjusted to the 2017 dollars of the UMCES 2021 report. A new suburban cell at $49,875 an acre and an urban retrofit at $186,750 bracket the practice’s range.
The 2011 estimates put a new suburban cell at about $50,000 an impervious acre and a retrofit in a dense urban street at $186,750, nearly four times as much. Maryland’s later project records agree with the high end: the median bioretention project treated an acre for $188,823 and the median micro-bioretention project for $278,276. The cheapest version of the practice, the planned subdivision cell that Prince George’s County began with, is the one retrofit programs rarely get to build.
The second price: upkeep
A bioretention cell is a garden with a job, and it needs the attention a garden needs. Inlets clog with sediment, mulch washes away, plants die in the first summer, the soil compacts, and a cell that bypasses its inflow removes nothing. The question is how much that upkeep costs, and the answer has moved. The Bay Program’s cost tool assumed 2.5 to 6 percent of construction cost a year. The 2011 Maryland estimates assumed as much as 4 to 7 percent. The 2021 update adopted Prince George’s County’s maintenance schedule, which comes to 11.5 percent a year for bioretention and 13.4 percent for infiltration and permeable pavement.
Source. Chesapeake Assessment Scenario Tool cost assumptions as reported in UMCES TS-772-21; King and Hagan, UMCES TS-626-11 (2011); UMCES TS-772-21 (2021).
Method. The UMCES 2021 figures follow Prince George’s County’s maintenance-intensity schedule (Exhibit 19). King and Hagan separately estimated $1,531 per impervious acre a year for bioretention upkeep.
19. Prince George’s County’s maintenance schedule, annualized: 11.5 percent a year
Source. Prince George’s County maintenance-intensity approach as adopted in UMCES TS-772-21 (2021).
Method. Routine work is 5 percent of installation cost each year. Level 1 work (10 to 15 percent, midpoint 12.5) recurs every three to five years, taken as four. Level 2 work (35 to 50 percent, midpoint 42.5) recurs every ten to fifteen years, taken as 12.5. Applied to Maryland project costs this is $7,598 per acre treated a year for a clay-soil cell and $5,313 for a sandy-soil cell.
20. What realistic upkeep and a 20-year life do to the annual cost of an acre
Source. UMCES TS-772-21 (2021), comparison of annualized costs per acre treated.
Method. CAST assumed lower maintenance shares and, for infiltration, a 50-year life; the 2021 report uses 20 years for bioretention, rain gardens, bioswales, filtering and infiltration and the maintenance shares in Exhibit 18. The report’s Table 14 puts the change at 1,125 percent for clay-soil bioretention ($1,058 to $12,957 an acre) and 758 percent for sandy-soil bioretention ($1,058 to $9,079). Filtering practices fall.
The maintenance assumption matters more than any argument about removal rates. Against the Bay Program’s assumptions, the 2021 report puts bioretention’s annual cost per acre up 758 percent on sandy soils ($1,058 to $9,079) and 1,125 percent on clay ($1,058 to $12,957).
Whether anyone keeps them
Whether the money is spent is another matter. Maryland law requires each facility to be inspected in its first year and at least every three years after; Prince George’s County’s manual calls for a look every month and within a day of any storm over an inch. The one broad outside check is a 2016 survey of the Baltimore region organized by Community and Environmental Defense Services with 17 organizations and 42 volunteers, in a region with about 20,000 facilities. It found 42 percent of the practices it visited in good condition, 33 percent in need of maintenance and 25 percent failing in ways that cancel most of their benefit. The six jurisdictions’ own 7,047 inspections that year issued correction notices in 32 percent of cases. Bioretention, micro-bioretention and rain gardens had the lowest failure rate of any practice in the survey, which is to say the cells people can see from the street are the ones that get fixed. Howard County rechecked 118 of the volunteers’ calls and agreed with 97 percent of them.
21. Condition of stormwater practices in the Baltimore region, 2016 volunteer survey
Source. Community and Environmental Defense Services, Stormwater BMP Greater Baltimore Survey 2016 (Richard Klein, July 22, 2016).
Method. A volunteer survey organized by an advocacy group with 17 organizations, limited to sites volunteers could reach; 336 practices were found and assessed. Howard County staff rechecked 118 assessments and found 97 percent correct. The same year the six jurisdictions’ 7,047 own inspections issued correction notices in 32 percent of cases. An earlier statewide check of infiltration practices, published in 1992, found half not working as designed within four years.
What the big programs are finding
The two largest green-infrastructure commitments in the region are being repriced as they are built. Philadelphia originally estimated $150,000 to $200,000 a greened acre. The Water Department now puts the fiscal 2020 price at $348,000, with upkeep of $10,000 to $12,000 an acre a year, and two of its employees told reporters in 2024 that the figure had passed $500,000. The program budget went from $2.4 billion to $4.5 billion between 2011 and 2021 while the acreage target held.
DC Water, told by its 2016 consent decree to build green infrastructure for 365 impervious acres in the Rock Creek sewershed, built a first project of 36 bioretention planters, 2 curb extensions and 39 permeable-pavement installations covering about 20 acres, then assessed the rest. It found that a fully green approach would cost nearly twice the gray alternative over thirty years and proposed a hybrid. In the Potomac sewershed the modified plan, green infrastructure with targeted sewer separation, shrinks a planned tunnel from 58 million to 30 million gallons.
22. Philadelphia’s cost per greened acre: $348,000 in fiscal 2020 against an original $150,000 to $200,000
Source. Philadelphia Water Department, response to “Unraveling the Facts” (2024); Grid Magazine with Chestnut Hill Local and Delaware Currents (May 30, 2024); William Penn Foundation.
Method. The $348,000 figure is the Water Department’s confirmed fiscal 2020 price per greened acre. The $500,000 figure is attributed to two anonymous department employees in a 2024 press investigation and is not an official estimate. Nominal dollars of different years.
Programs count acres differently, and the differences are not small. Maryland’s accounting credits an impervious acre as restored when an approved practice treats it; the Clean Water Partnership counts “credit acres”; Philadelphia counts greened acres with the first inch managed. With that warning, the per-acre figures line up in a recognizable order. Maryland’s large jurisdictions projected $379.7 million of BMP costs, excluding debt service, for 9,190 acres in fiscal 2023 and 2024, about $41,000 an acre. Prince George’s County’s MS4 permit requirement, 15,000 acres for $1.2 billion, works out at about $80,000 an acre, and its partnership’s record, $329.6 million for 4,658 credit acres, at about $71,000. A bioretention project alone runs near $190,000, and a Philadelphia greened acre $348,000.
23. Dollars per acre, six ways of counting
Source. MDE, 2024 Stormwater Financial Assurance Plan Annual Report, Table 4; EPA G3 (archived), Prince George’s County permit requirement; Clean Water Partnership dashboard (March 2026); King and Hagan (2011); UMCES TS-772-21 (2021); Philadelphia Water Department (2024).
Method. Derived: $379,717,185 (BMP costs, excluding debt service) ÷ 9,190 acres = $41,319; $1.2 billion ÷ 15,000 acres = $80,000; $329.6 million (program costs expended, March 2026) ÷ 4,658 credit acres = $70,760. Dollar years differ and are not adjusted. The bases are not interchangeable: a greened acre manages one inch of rain, a Maryland restored acre is a permit credit that may be a fraction of an acre of practice footprint.
Who pays
The money is mostly local. Nine of Maryland’s ten large jurisdictions (Montgomery County was not required to report) put $200.9 million into their watershed protection and restoration funds in fiscal 2023, $83.7 million of it raised by stormwater fees on 699,981 properties; they spent $113.3 million on capital work and $58.8 million on operations and maintenance. Residential fees run from a penny a year in Frederick County to $170. Carroll and Harford pay from general taxes, and Baltimore County repealed its fee in 2017. Prince George’s County raised $77.6 million, Baltimore City $42.9 million and Anne Arundel $26.2 million. The District funds its work through DC Water’s impervious area charge and the city’s stormwater fee, and backs its credit market with an $11.5 million price-lock commitment.
24. Watershed protection and restoration fund revenue, Maryland’s large jurisdictions, fiscal 2023
Source. Maryland Department of the Environment, 2024 Stormwater Financial Assurance Plan Annual Report.
Method. Revenue reported to each jurisdiction’s watershed protection and restoration fund, which includes fee revenue and other transfers; the nine reporting jurisdictions (Montgomery County was not required to report) together reported $200.9 million (Table 6), of which $83.7 million was stormwater remediation fees. Frederick County’s fee is one cent a year; Carroll and Harford fund from general revenue. Baltimore County repealed its fee effective July 1, 2017. The nine bars are rounded and sum to $201.1 million; the report’s total is $200,862,536.
Three conclusions follow from the three parts. First, bioretention is a sound practice in the right ground: where soils infiltrate, it removes water and with it most of what the water carries, at a cost per pound that compares with the alternatives. Second, in the clay that underlies most of the region’s suburbs it is a filter, and an expensive one, that needs a saturated zone and a low-phosphorus soil to do what it is credited with. Third, the cost that decides the matter is not construction but the decades of upkeep after it, and the region has only begun to budget for them honestly. The pounds the Bay needs are bought most cheaply where the rain falls on farmland, and most expensively where it falls on a street. The region will go on buying both.
Limitations (8)
- Method. The UMCES cost-per-pound figures combine measured project costs with Bay-model credits for pounds removed; for clay-soil bioretention the underlying project costs range from $3,000 to $1.96 million an acre (17 projects), so the median hides wide dispersion. Bioswale, sweeping and permeable pavement rest on one or two projects.
- Method. King and Hagan’s 2011 figures are planning-level averages in 2011 dollars including land; they were not adjusted to the 2017 dollars of the 2021 report or to today’s prices.
- Coverage. The 2016 Baltimore survey is advocacy-group data gathered by volunteers from publicly reachable sites; it assessed 336 practices, a sample of the region’s roughly 20,000. Systematic inspection pass rates for bioretention in Montgomery, Fairfax and Prince George’s counties were not retrieved.
- Conflicting sources. Philadelphia’s above-$500,000 figure comes from two anonymous Water Department employees quoted in a 2024 press investigation; the department’s confirmed figure is $348,000 for fiscal 2020.
- Unverified. The county committee briefing’s figures for the Clean Water Partnership (about $378 million spent, more than $270 million of it with minority-owned and local firms) could not be located at any address; this page uses the partnership’s own dashboard (updated March 2026) for both its spending and its acres. Neither has been independently audited.
- Coverage. DC Water’s and DOEE’s fee levels and collections were not quantified; only the price-lock commitment is given. The “nearly twice” cost finding is DC Water’s own practicability assessment.
- Method. Maryland’s fund revenue includes transfers other than fees in some jurisdictions; the report’s fee total ($83.7 million) is less than the sum of the jurisdiction revenues charted.
- Method. Baltimore City’s fiscal 2023 figures in the Financial Assurance Plan report are $42.7 million of stormwater fees ($42,736,661) and $42.9 million of total fund sources ($42,851,240); Exhibit 24 charts the total.
Sources (16)
- University of Maryland Center for Environmental Science: Price, Flemming and Wainger, Cost Analysis of Stormwater and Agricultural Practices for Reducing Nitrogen and Phosphorus Runoff in Maryland, UMCES TS-772-21 (March 2021); King and Hagan, Costs of Stormwater Management Practices in Maryland Counties, UMCES TS-626-11 (October 2011)
- Maryland Department of the Environment: 2024 Stormwater Financial Assurance Plan Annual Report (MSAR #10954)
- Prince George’s County Department of the Environment: Stormwater Best Management Practices Inspection Manual (July 2009)
- St. Mary’s County Department of Public Works: stormwater facility inspection program (COMAR 26.17.02.11)
- Chesapeake Stormwater Network: Technical Bulletin No. 10, Bioretention Illustrated
- ITRC: Stormwater BMP Performance Evaluation, Appendix F: bioretention information sheet
- Community and Environmental Defense Services: Stormwater BMP Greater Baltimore Survey 2016 (July 22, 2016)
- Lindsey, Roberts and Page, Inspection and maintenance of infiltration facilities, Journal of Soil and Water Conservation (1992)
- Philadelphia Water Department: response to “Unraveling the Facts” (2024)
- Grid Magazine: with Chestnut Hill Local and Delaware Currents, on Green City, Clean Waters costs (May 30, 2024)
- William Penn Foundation: Sustainable Funding for Philadelphia’s Green City, Clean Waters Plan
- DC Water: practicability assessment for Rock Creek green infrastructure; 2016 Green Bond Report
- EPA: Getting Realistic: Using Gray and Green Infrastructure in DC; Nutrient and Stormwater Trading Case Study: the District’s Stormwater Retention Credit program (2020); Green Streets, Green Jobs, Green Towns: Prince George’s County Clean Water Partnership (archived)
- Corvias and Prince George’s County: Clean Water Partnership dashboard, “By the Numbers” (updated March 2026)
- UNC Environmental Finance Center: Prince George’s County Clean Water Partnership case study
- Maryland Association of Counties: Conduit Street, on the 2015 stormwater fee bill
Read next
- Every Dollar to the Chesapeake Where the money for the Chesapeake restoration comes from, which agency holds it and who is paid to do the work.
- Keeping Nitrogen Out of the Chesapeake How much nitrogen is kept out of the Chesapeake Bay, how much still gets in and what each pound costs.