From Study XX · Part 3 of 3, Exhibit 23
Dollars per acre, six ways of counting
Source. MDE, 2024 Stormwater Financial Assurance Plan Annual Report, Table 4; EPA G3 (archived), Prince George’s County permit requirement; Clean Water Partnership dashboard (March 2026); King and Hagan (2011); UMCES TS-772-21 (2021); Philadelphia Water Department (2024).
Method. Derived: $379,717,185 (BMP costs, excluding debt service) ÷ 9,190 acres = $41,319; $1.2 billion ÷ 15,000 acres = $80,000; $329.6 million (program costs expended, March 2026) ÷ 4,658 credit acres = $70,760. Dollar years differ and are not adjusted. The bases are not interchangeable: a greened acre manages one inch of rain, a Maryland restored acre is a permit credit that may be a fraction of an acre of practice footprint.
| Program or estimate | Cost per acre ($) | Basis |
|---|---|---|
| Maryland large jurisdictions, BMP costs excluding debt service, FY23–24 | 41,319 | per impervious acre restored |
| Prince George’s County permit requirement to 2025 | 80,000 | per impervious acre |
| Clean Water Partnership, spent to date | 70,760 | per credit acre |
| King and Hagan, urban bioretention retrofit (2011) | 186,750 | per impervious acre |
| Maryland median bioretention project (2017 $) | 188,823 | per impervious acre |
| Philadelphia greened acre (FY2020) | 348,000 | per greened acre |