From Study XX · Part 3 of 3, Exhibit 17

Planning-level construction cost per impervious acre, Maryland, 2011

Source. King and Hagan, Costs of Stormwater Management Practices in Maryland Counties, UMCES TS-626-11, report to MDE (October 2011).

Method. Planning-level averages in 2011 dollars, including land at $50,000 an acre; not adjusted to the 2017 dollars of the UMCES 2021 report. A new suburban cell at $49,875 an acre and an urban retrofit at $186,750 bracket the practice’s range.

PracticeInitial cost per impervious acre ($, 2011)
Street sweeping (equipment)6,049
Vegetated open channel26,000
Wet pond, new26,115
Bioswale, new44,000
Dry extended detention, new44,000
Bioretention, new, suburban49,875
Filtering practice, above ground54,000
Stream restoration64,500
Wet pond, retrofit65,998
Infiltration with sand66,250
Dry extended detention, retrofit72,500
Bioretention, retrofit, highly urban186,750
Permeable pavement, without sand239,580
Permeable pavement, with sand335,412