From Study XX · Part 3 of 3, Exhibit 17
Planning-level construction cost per impervious acre, Maryland, 2011
Source. King and Hagan, Costs of Stormwater Management Practices in Maryland Counties, UMCES TS-626-11, report to MDE (October 2011).
Method. Planning-level averages in 2011 dollars, including land at $50,000 an acre; not adjusted to the 2017 dollars of the UMCES 2021 report. A new suburban cell at $49,875 an acre and an urban retrofit at $186,750 bracket the practice’s range.
| Practice | Initial cost per impervious acre ($, 2011) |
|---|---|
| Street sweeping (equipment) | 6,049 |
| Vegetated open channel | 26,000 |
| Wet pond, new | 26,115 |
| Bioswale, new | 44,000 |
| Dry extended detention, new | 44,000 |
| Bioretention, new, suburban | 49,875 |
| Filtering practice, above ground | 54,000 |
| Stream restoration | 64,500 |
| Wet pond, retrofit | 65,998 |
| Infiltration with sand | 66,250 |
| Dry extended detention, retrofit | 72,500 |
| Bioretention, retrofit, highly urban | 186,750 |
| Permeable pavement, without sand | 239,580 |
| Permeable pavement, with sand | 335,412 |