What DC’s Sewer Tunnels Bought
Sewer overflow at every District outfall, 2005–2026, from DC Water’s quarterly reports; what Clean Rivers cost; and the charge against the 2017 plan.
9 min read · 12 exhibits
About a third of the District is served by combined sewers, single pipes that carry both sewage and stormwater. When rain exceeds their capacity, the excess, a mix of the two, discharges through outfalls into the Anacostia River, the Potomac River and Rock Creek, as DC Water’s quarterly operations reports describe it. Under a 2005 consent decree DC Water is building the Clean Rivers program of storage tunnels and green infrastructure to cut those combined sewer overflows; its 2002 Long Term Control Plan set the target at a 96% cut in overflow volume in an average year. The first Anacostia tunnel was placed in operation on March 20, 2018 and the Northeast Boundary Tunnel on September 15, 2023, according to DC Water’s consent decree status report for the third quarter of 2026.
Every quarter since 2005 DC Water has reported the overflow at each outfall to EPA and the District. This study assembles those 87 quarterly tables, from the first quarter of 2005 to the third quarter of 2026, into one record of 55 outfalls, and sets beside it what the program has cost and what ratepayers are charged for it. Before 2018 every value is modeled, an estimate from DC Water’s collection system model run on observed rain; from 2018 most Anacostia outfalls are metered. The two are labeled throughout. Pipes and Tunnels, part of The Chesapeake and the Region’s Waters, covers the District totals by river, contract values and household bills; they are not repeated here.

The Anacostia River at the Washington Navy Yard, April 1973. The National Archives record attributes the brown color of the water to excess silt.
Outfall by outfall
This section shows the overflow at each outfall, year by year. The largest single source before the tunnels was Northeast Boundary, outfall 019, on the Anacostia. Its modeled overflow averaged 850.3 million gallons a year in 2005–2017, from 415.8 million in 2007 to 1,975.8 million in 2005 (Exhibit 1). After the first tunnel opened, Northeast Boundary still overflowed in heavy storms because the Northeast Boundary Tunnel that serves it was not finished: 244.7 million gallons in 2023 from its two outfalls, 232.0 million of it at outfall 019. In 2024, the first full year with that tunnel, the two Northeast Boundary outfalls released 86.19 million gallons, 84.23 million of it through the tunnel overflow; in 2025 they released 0.07 million.
1. Northeast Boundary’s outfalls averaged 850.3 million gallons of modeled overflow a year in 2005–2017; in 2025 they released 0.07 million, metered
Source. DC Water, Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, combined sewer system modeled and metered results tables.
Method. Outfall 019 and the Northeast Boundary tunnel overflow, 019A, added. Before 2018 outfall 019 had two rows, swirl effluent and bypass, summed here.
Exhibit 2 shows every outfall in every year. The Anacostia outfalls are dark before 2018 and pale after it, as the tunnel system began taking their flow; the tables list four of them, 015 to 018, as consolidated into it from 2018. The Potomac outfalls, 020 to 029, stay dark across the whole period: the Potomac River Tunnel that will take their flow is required to be in operation by February 8, 2030. In Rock Creek the largest is Piney Branch, outfall 049.
2. Each District outfall’s overflow in each year from 2005 to September 2026: the Anacostia outfalls fell after 2018 and the Potomac outfalls did not
Source. DC Water, Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, combined sewer system modeled and metered results tables.
Method. Annual values add the four quarterly tables; 2026 adds January to September. Outfalls are DC Water’s NPDES outfall numbers.
Comparing averages across periods takes out some of the year-to-year swing in rain. The District’s outfalls released an average of 2,079.8 million gallons a year in 2005–2017, 1,388.5 million in 2018–2022 and 381.1 million in 2024–2025. The Anacostia outfalls fell from 1,345.4 million gallons a year to 46.9 million; the Potomac outfalls rose to 987.9 million in 2018–2022, a period that included 2018, the wettest year at National Airport on record according to a DC Water release of January 7, 2019, and were 325.0 million in 2024–2025. Of the 42 outfalls with modeled overflow before the tunnels, 31 were closed or below 1 million gallons a year in 2024–2025 (Exhibit 3). Outfall 028, at 36th and M Streets in Georgetown, averaged 9.06 million gallons a year in 2024–2025 against 7.00 million in 2005–2017, the one increase.
3. Of the 42 outfalls with modeled overflow in 2005–2017, 31 were closed or averaged under 1 million gallons a year in 2024–2025; one, outfall 028, averaged more
Source. DC Water, Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, combined sewer system modeled and metered results tables.
Method. Averages divide each period’s total by its number of years: 13, 5 and 2. 2023 is left out because the Northeast Boundary Tunnel opened in September of that year. Zero is plotted at the left edge.
Highest and lowest
This section lists the extremes in the record. The largest overflow at one outfall in one year was Northeast Boundary’s in 2005; the outfall with the most overflow events in a year was 028, with 152 in 2012, and it still had the most in 2025, 46 (Exhibit 4). The District total was highest in 2005, 5,827.6 million gallons, and lowest in 2025.
4. The largest outfall-year was Northeast Boundary in 2005, 1,975.8 million gallons; the smallest District total was 2025’s, 253.1 million
| Measure | Outfall | Location | River | Year | Value | Unit | Modeled or metered |
|---|---|---|---|---|---|---|---|
| Largest outfall-year, 2005–2026 | 019 | Northeast Boundary | Anacostia | 2005 | 1975.8 | million gallons | modeled |
| Largest District total, full years | All outfalls | All three | 2005 | 5827.6 | million gallons | modeled | |
| Smallest District total, full years | All outfalls | All three | 2025 | 253.1 | million gallons | modeled and metered | |
| Largest fall in average annual overflow, 2005–2017 to 2024–2025 | 019 | Northeast Boundary | Anacostia | 2005–2017 to 2024–2025 | −849.3 | million gallons a year | |
| Largest rise in average annual overflow, 2005–2017 to 2024–2025 | 028 | 36th and M Streets, NW | Potomac | 2005–2017 to 2024–2025 | 2.06 | million gallons a year | |
| Largest outfall overflow, 2025 | 021 | Northeast of Roosevelt Bridge, NW | Potomac | 2025 | 183.69 | million gallons | modeled |
| Smallest nonzero outfall overflow, 2025 | 043 | Adams Mill Road south of Irving Street, NW | Rock Creek | 2025 | 0.002 | million gallons | modeled |
| Most overflow events at one outfall in a year | 028 | 36th and M Streets, NW | Potomac | 2012 | 152 | events | modeled |
| Most overflow events at one outfall, 2025 | 028 | 36th and M Streets, NW | Potomac | 2025 | 46 | events | modeled |
Source. DC Water, Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, combined sewer system modeled and metered results tables.
Method. Every value is a cell of Exhibits 1, 2, 3 or 5. Full years only for District totals; 2026 is left out.
What is left
This section shows where the overflow now comes from. Fifteen outfalls overflowed in 2025, and one of them accounts for most of the volume: outfall 021, which discharges to the Potomac northeast of the Roosevelt Bridge, released 183.69 million of the District’s 253.07 million gallons (Exhibit 5). The four outfalls assigned to the Potomac River Tunnel in DC Water’s 2015 plan modification, 020, 021, 022 and 024, released 214.16 million gallons, 84.6% of the total. The pattern held in the first nine months of 2026: 133.93 million of 207.81 million gallons, 64.4%, came from outfall 021. DC Water’s October 2026 overflow report expects the Potomac River Tunnel to reduce overflow to the Potomac by 93% in an average year.
5. Outfall 021, northeast of the Roosevelt Bridge, released 183.69 million gallons in 2025, 72.6% of the District’s overflow
Source. DC Water, Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, combined sewer system modeled and metered results tables.
Method. Fifteen outfalls overflowed in 2025; the other 27 in the tables reported none. Potomac outfalls 020–029 and Rock Creek outfalls are modeled; 003A and the Anacostia outfalls are metered.

The Potomac looking northwest from Arlington Memorial Bridge to the Theodore Roosevelt Bridge, October 7, 2016. Outfall 021 discharges on the District shore northeast of the Roosevelt Bridge.
Photograph: Famartin, October 7, 2016. CC BY-SA 4.0 (creativecommons.org/licenses/by-sa/4.0).
Three Georgetown outfalls, 027, 028 and 029, were to be controlled with green infrastructure under the 2015 modification. DC Water’s August 2020 practicability assessment found that approach not practicable for 027 and 028, citing the difficulty of building in the Georgetown Historic District and objections from review bodies there, and not cost-effective for the Potomac sewershed as a whole.

The Georgetown waterfront downstream of the Key Bridge, with the Whitehurst Freeway along the shore; outfall 027 is on Water Street west of 31st Street, on this stretch. Undated; the Library of Congress record says the documentation was compiled after 1933.
What the tunnels captured
This section shows the tunnels’ own meters. From March 2018 to December 2025 the Anacostia River tunnel system took in 21,237 million gallons in 398 events, captured 19,579 million, which is conveyed to the Blue Plains treatment plant, and let 1,658 million overflow, according to DC Water’s February 2026 committee report (Exhibit 6). In calendar 2025 it captured 1,803 million gallons and let 5 million overflow. In 2018, its first year and the wettest on record at National Airport, it captured 4,570 million gallons, 89% of the flow, per DC Water’s release.
6. The Anacostia tunnel system captured 19,579 million gallons from March 2018 to December 2025 and let 1,658 million overflow, 92.2% captured
Source. DC Water, Environmental Quality and Operations Committee meeting package, February 19, 2026, p. 69; news release, January 7, 2019.
Method. Volumes as the committee table reports them: volume captured and volume to combined sewer overflow. Totals add the two.

The Blue Plains Advanced Wastewater Treatment Plant on the Potomac in southwest Washington, about 2016. Flow captured by the Anacostia tunnels is conveyed here for treatment, according to DC Water.
Photograph: U.S. Environmental Protection Agency, about 2016. Public domain.
What it cost
This section traces the price. The 2002 plan estimated a capital cost of $1.265 billion in 2001 dollars. DC Water’s financial reports and budgets put the program at $2.6 billion to $2.8 billion from fiscal 2009 through 2018, and its approved capital program now carries a lifetime budget of $3,290.8 million in fiscal 2026 and $3,560.8 million in fiscal 2027, 37.0% above the $2.6 billion in the budget adopted in December 2016 (Exhibit 7). A lifetime budget covers spending before, during and after the ten-year plan; it is not a final cost, which DC Water has not published.
By receiving water, the Anacostia’s lifetime budget, $1,907.1 million, is the largest, and its outfalls show the largest reduction (Exhibit 8). Rock Creek’s budget rose from $203.7 million in fiscal 2026 to $494.2 million in fiscal 2027.
7. DC Water’s budgets put Clean Rivers at $2.6 billion in December 2016 and $3.56 billion in March 2026; the 2002 plan priced it at $1.265 billion in 2001 dollars
Source. DC Water, Long Term Control Plan, July 2002; comprehensive annual financial reports for fiscal 2009, 2011 and 2012; Long Term Control Plan Modification for Green Infrastructure, May 2015; approved budgets for fiscal 2018, 2019, 2026 and 2027.
Method. Solid dots are nominal estimates whose price basis the documents do not state; the hollow dot is in 2001 dollars. 2025 and 2026 are lifetime budgets.
8. The fiscal 2027 lifetime budget is $1.91 billion for the Anacostia, $1.16 billion for the Potomac and $0.49 billion for Rock Creek
| Receiving water | Lifetime budget, fiscal 2026 ($ millions) | Lifetime budget, fiscal 2027 ($ millions) | Average overflow 2005–2017, modeled (MG) | Average overflow 2024–2025, modeled and metered (MG) | Main facility | In operation |
|---|---|---|---|---|---|---|
| Anacostia | 1,927.9 | 1,907.1 | 1,345.41 | 46.9 | Anacostia River tunnel system | March 20, 2018 (first segment); September 15, 2023 (Northeast Boundary Tunnel) |
| Potomac | 1,159.2 | 1,159.5 | 646.12 | 324.99 | Potomac River Tunnel | Required by February 8, 2030 |
| Rock Creek | 203.7 | 494.2 | 88.26 | 9.2 | Piney Branch storage tunnel and green infrastructure | Storage required by November 23, 2029 |
Source. DC Water, approved capital improvement programs for fiscal 2026 and fiscal 2027; Long Term Control Plan consent decree status report, third quarter 2026; quarterly operations reports, 2005–2025.
Method. Overflow in million gallons (MG) a year, the sum of each river’s outfalls in Exhibit 3. For the Anacostia, $1,907.1 million ÷ (1,345.41 − 46.90) MG = $1.47 of budget per gallon of average annual overflow removed.
The 2016 decree modification let DC Water try green infrastructure at Piney Branch, outfall 049, instead of a 9.5-million-gallon storage tunnel. Its June 2020 assessment found green infrastructure practicable to build and operate but not on cost: managing 365 impervious acres would cost $407 million over 30 years against $211 million for storage (Exhibit 9). DC Water chose a hybrid of green infrastructure, a 4.2-million-gallon storage tunnel and credit for stormwater controls built under District rules, at $207 million. The consent decree, as DC Water’s status report lists it, requires the storage to be in operation by November 23, 2029.
9. For the Piney Branch outfall, DC Water’s 2020 assessment put an all-green plan at $407 million over 30 years, against $211 million for storage and $207 million for the hybrid it chose
Source. DC Water, Practicability Assessment for Rock Creek Green Infrastructure, June 2020, Tables ES-4 and ES-5.
Method. Net present value over 30 years combines capital cost and operations and maintenance, in 2020 dollars, as DC Water computed it.

Excavation for an expansion of the Blue Plains sewage treatment plant, April 1973.
The charge against the 2017 plan
This section tests whether ratepayers pay less than DC Water projected. Since May 2009 DC Water has billed the Clean Rivers Impervious Area Charge to recover the program’s cost, monthly per equivalent residential unit (ERU) of impervious surface on each property. The plan in force through 2017, adopted with the fiscal 2018 budget on December 1, 2016, projected the charge rising from $25.18 in fiscal 2018 to $44.40 in fiscal 2026; the fiscal 2019 budget shows the same plan reaching $45.99 in fiscal 2027. The charge was $24.23 in fiscal 2026 and is $25.50 in fiscal 2027, 44.6% below the projection (Exhibit 10). It fell to $18.14 in fiscal 2023, and DC Water’s current plan, adopted March 5, 2026, has it peaking at $32.51 in fiscal 2031.
DC Water’s documents give three reasons the charge came in lower while the cost estimate rose. Federal appropriations are not among them: the 2016 plan assumed none beyond the special Congressional appropriation, and Pipes and Tunnels covers the amounts.
- Part of the cost moved to the sewer rate. From fiscal 2020 the Board shifted 18% of Clean Rivers costs from the charge to the sewer volumetric rate, rising to 28% in fiscal 2021 and 37% from fiscal 2022, on an assessment that about 37% of the volume in the tunnels is wastewater (fiscal 2026 rates and revenue).
- Debt. The fiscal 2019 budget credits Century Bonds, refinancing and restructuring debt “so the relief is provided to today’s customers”; it does not say how much each saved.
- Schedule. The 2016 modification moved the Potomac and Rock Creek deadlines from 2025 to 2030; the 2015 modification gives affordability as one reason, projecting that the original schedule, with other sewer and wastewater work, would be unaffordable for more than 40% of households by 2018.
The shift accounts for part of the gap but not all of it. Adding the 37% back to the fiscal 2026 charge gives $38.46, still $5.94 below the $44.40 projected (Exhibit 11). The sewer rate moved the other way: $12.52 per hundred cubic feet (Ccf) in fiscal 2026, against $8.86 if it had risen by the 5.0% a year the 2016 plan stated (Exhibit 12). That rate also pays for sewer work outside Clean Rivers, so the difference cannot all be assigned to the shift.
10. The Clean Rivers charge is $25.50 per ERU a month in fiscal 2027; the plan in force in 2017 projected $45.99
Source. DC Water, approved budgets for fiscal 2018 (adopted December 1, 2016), fiscal 2019 (adopted March 1, 2018) and fiscal 2027 (adopted March 5, 2026); fiscal 2025 annual comprehensive financial report, statistical section.
Method. ERU: equivalent residential unit, the median impervious area of a single-family property, as DC Water’s fiscal 2026 budget glossary defines it. The plan in force in 2017 is the one adopted December 1, 2016; its fiscal 2027 value is from the fiscal 2019 budget.
11. Even with the 37% shifted to the sewer rate added back, the fiscal 2026 charge works out to $38.46, below the $44.40 projected
Source. DC Water, approved fiscal 2018 budget, p. III-20; approved fiscal 2026 budget, rates and revenue.
Method. Added back: $24.23 ÷ (1 − 0.37) = $38.46, assuming the same number of ERUs and that the 37% shift applies to the whole charge.
12. The sewer rate reached $12.52 per Ccf in fiscal 2026, 41.2% above the $8.86 that the 2016 plan’s 5.0% a year implies
Source. DC Water, fiscal 2025 annual comprehensive financial report, statistical section, Exhibit 8; approved fiscal 2027 budget, rates and revenue; approved fiscal 2018 budget.
Method. Plan path: the fiscal 2018 rate, $6.00, raised 5.0% a year, the increase the 2016 plan stated for water and sewer rates through fiscal 2026.
Limitations (16)
- Method. Overflow values before 2018 are modeled: DC Water’s collection system model run on observed rain, as reported in the quarterly tables. From the second quarter of 2018 the tables mark Anacostia outfalls 007–012, 019, 019A and the Potomac tunnel outfall 003A as metered; the rest stay modeled. Modeled and metered values are not measured the same way, and Exhibits 1–3 and 5 compare them across that line.
- Method. Annual values add four quarterly tables per outfall; 2026 covers January to September. Before 2018 outfall 019 is reported in two rows, swirl effluent and bypass; volumes are added, and for events the larger of the two counts is used so an event is not counted twice.
- Method. The 2005–2009 reports print river and District totals rounded to whole million gallons; the outfall rows sum to within 0.7 million gallons of those totals (2005 third quarter, 2007 second quarter).
- Method. Three reports are scanned images without a usable text layer (fourth quarter 2018, first quarter 2019, third quarter 2026); their tables were read from the page images. Each transcription matches the printed river subtotals and total to within 0.01 million gallons.
- Conflicting sources. Quarter labels in three reports disagree between the two header lines: the second-quarter 2019 table is headed “Period: April, May, June 2019” and “QuarterlyReport_2019Q3”; the fourth-quarter 2019 table reads “2020” in its period line; the third-quarter 2026 table reads “Q2 2026”. Each is assigned by the line that agrees with the report’s title.
- Conflicting sources. EPA’s ECHO discharge monitoring reports carry flow records for outfall 019 only, from January 2010 to July 2018; for 2010–2017, monthly average flow times days gives 113.6 to 977.9 million gallons a year, against DC Water’s modeled 495.5 to 1,012.1 million for the same years. ECHO holds no records for the other combined sewer outfalls, so it could not be used to check them.
- Conflicting sources. Anacostia tunnel capture from March 2018: 19,579 million gallons to December 2025 in the committee package table (p. 69) and “over 19.65 billion gallons” on p. 78 of the same package; the fiscal 2025 financial report gives nearly 19.5 billion through September 2025. Exhibit 6 uses the table.
- Coverage. Overflow depends on rain, and no exhibit adjusts for it; the period averages in Exhibit 3 reduce but do not remove the effect. 2018 was the wettest year on record at National Airport.
- Coverage. Outfalls separated or consolidated into the tunnel system drop out of the tables; their flow is counted in the tunnel figures of Exhibit 6, not in outfall values.
- Method. “The plan in force in 2017” is the ten-year plan adopted December 1, 2016 with the fiscal 2018 budget, the last plan adopted before March 1, 2018; its fiscal 2027 value, $45.99, is the “last year’s Board adopted plan” series in the fiscal 2019 budget.
- Method. The added-back charge in Exhibit 11 assumes the same number of ERUs and that the 37% shift applies to the whole charge; DC Water does not publish the charge without the shift.
- Method. The 5.0% sewer-rate path in Exhibit 12 applies the increase the fiscal 2018 budget stated for water and sewer rates to the fiscal 2018 sewer rate; the budget does not print a sewer rate for each year.
- Unverified. Final cost. Lifetime budgets are budgets, not spending; DC Water has not published a final cost for the program or for the completed Anacostia tunnels.
- Conflicting sources. The fiscal 2009 financial report gives the program’s cost as $2.7 billion in two passages and $2.6 billion in a third; Exhibit 7 uses $2.7 billion.
- Coverage. Cost estimates before fiscal 2025 do not state a price basis except the 2002 plan’s 2001 dollars, so Exhibit 7 compares nominal figures of different years.
- Revisions. Several quarterly reports were posted as revised (2014, first quarter 2015, second quarter 2018); this study uses the versions posted on DC Water’s publications page in November 2026. Modeled values may be revised in later reports.
Sources (3)
- DC Water: Combined Sewer Overflow Facilities quarterly operations reports, first quarter 2005 to third quarter 2026, 2005–2026; Long Term Control Plan consent decree quarterly status reports, 2005–2026; Long Term Control Plan Consent Decree Status Report, Quarter No. 3, 2026, October 2026; Combined Sewer System Long Term Control Plan, final report, July 2002; Long Term Control Plan Modification for Green Infrastructure, May 2015; Combined sewer overflow report, October 2026; Environmental Quality and Operations Committee meeting package, February 19, 2026; DC Water’s Anacostia River Tunnel saves river from 4.5 billion gallons of sewage overflow in 2018, January 7, 2019; Practicability Assessment for Rock Creek Green Infrastructure, June 2020; Practicability Assessment for Potomac River Green Infrastructure, August 2020; Approved Fiscal Year 2018 Budgets, adopted December 1, 2016; Approved Fiscal Year 2019 Budgets, adopted March 1, 2018; Approved FY 2026 Budgets, Section IV: Rates and Revenue, adopted March 6, 2025; Approved FY 2026 Budgets, Capital Improvement Program, adopted March 6, 2025; Approved FY 2027 Budgets, Section IV: Rates and Revenue, adopted March 5, 2026; Approved FY 2027 Budgets, Capital Improvement Program, adopted March 5, 2026; Fiscal Year 2025 Annual Comprehensive Financial Report, Statistical Section, 2026; Comprehensive Annual Financial Report, fiscal 2009, 2010; Comprehensive Annual Financial Report, fiscal 2011, 2012; Comprehensive Annual Financial Report, fiscal 2012, 2013; Combined Sewer System, 2026; FY 2026 Budgets: Glossary, Acronyms and Resolutions, 2025
- U.S. Environmental Protection Agency: ECHO Detailed Facility Report, Blue Plains (NPDES DC0021199), 2026
- Higgins Strategy: The Chesapeake and the Region’s Waters, Part 2: Pipes and Tunnels, 2026
Read next
- Federal Jobs in the Region Since January 2025 The region fell faster than the country
- Every Dollar to the Chesapeake Where the money for the Chesapeake restoration comes from, which agency holds it and who is paid to do the work.
- Keeping Nitrogen Out of the Chesapeake How much nitrogen is kept out of the Chesapeake Bay, how much still gets in and what each pound costs.
A principal of Higgins Strategy is employed by a contractor in the regional stormwater market. No figure in this study was obtained through that employment, and no company was added to or removed from the data on that account.