From Study XXX, Exhibit 8

The fiscal 2027 lifetime budget is $1.91 billion for the Anacostia, $1.16 billion for the Potomac and $0.49 billion for Rock Creek

Receiving waterLifetime budget, fiscal 2026 ($ millions)Lifetime budget, fiscal 2027 ($ millions)Average overflow 2005–2017, modeled (MG)Average overflow 2024–2025, modeled and metered (MG)Main facilityIn operation
Anacostia1,927.91,907.11,345.4146.9Anacostia River tunnel systemMarch 20, 2018 (first segment); September 15, 2023 (Northeast Boundary Tunnel)
Potomac1,159.21,159.5646.12324.99Potomac River TunnelRequired by February 8, 2030
Rock Creek203.7494.288.269.2Piney Branch storage tunnel and green infrastructureStorage required by November 23, 2029

Source. DC Water, approved capital improvement programs for fiscal 2026 and fiscal 2027; Long Term Control Plan consent decree status report, third quarter 2026; quarterly operations reports, 2005–2025.

Method. Overflow in million gallons (MG) a year, the sum of each river’s outfalls in Exhibit 3. For the Anacostia, $1,907.1 million ÷ (1,345.41 − 46.90) MG = $1.47 of budget per gallon of average annual overflow removed.