Where legal deadlines have moved, they have moved later: the District’s sewer decree from 2025 to 2030, and Baltimore has asked to move its decree end from 2030 to 2046 First documented and current dates; a dashed line runs to a proposed date not approved 2015 2025 2035 2045 DC Clean Rivers decree, final compliance Legal: 2025 to 2030 Baltimore sewer decree, completion Legal: January 2016 to December 31, 2030; December 31, 2046 proposed Baltimore, last four overflow structures Legal: July 1, 2022 to July 31, 2030 HRSD decree, Lafayette pump stations Legal: May 5, 2027 to May 5, 2029 Alexandria RiverRenew, statutory date Legal: July 1, 2025 to July 1, 2026 Bay nitrogen and phosphorus targets Voluntary: 2025 to 2040 Baltimore Harbor swimmable and fishable Voluntary: 2020 to 2030 Anacostia swimmable (District target) Voluntary: 2032 to 2027 Mid-Bay James Island, construction start Project schedule: 2024 to April 2026 Loudoun Westpark stream restoration Project schedule: 2027 to March 2029 First documented and current dates; a dashed line runs to a proposed date not approved 2015 2025 2035 2045 DC Clean Rivers decree, final compliance Legal: 2025 to 2030 Baltimore sewer decree, completion Legal: January 2016 to December 31, 2030; December 31, 2046 proposed Baltimore, last four overflow structures Legal: July 1, 2022 to July 31, 2030 HRSD decree, Lafayette pump stations Legal: May 5, 2027 to May 5, 2029 Alexandria RiverRenew, statutory date Legal: July 1, 2025 to July 1, 2026 Bay nitrogen and phosphorus targets Voluntary: 2025 to 2040 Baltimore Harbor swimmable and fishable Voluntary: 2020 to 2030 Anacostia swimmable (District target) Voluntary: 2032 to 2027 Mid-Bay James Island, construction start Project schedule: 2024 to April 2026 Loudoun Westpark stream restoration Project schedule: 2027 to March 2029
Source. Federal Register, proposed amendment to the DC Water consent decree, 2015 ; DC Water decree report Q2 2026 ; MDE, modified Baltimore consent decree ; Baltimore Brew, 2025 ; Baltimore MCD quarterly report 34 ; HRSD decree, Seventh Amendment ; ALXnow ; Watershed Agreement 2025 ; Chesapeake Bay Magazine ; The Wash ; AJOT, 2021 ; USACE via DVIDS ; Loudoun County .
Method. Open circle: first documented date; filled: current date; dashed: proposed, not approved. Baltimore’s last four overflow structures: decree date against the city’s projection. Baltimore Harbor set a 2030 vision after its 2020 goal passed. Bay targets: the 2025 deadline against the Agreement’s 2040 date for plans to meet revised targets.
Data table Schedule Kind Original Current Proposed Shift (years, to latest date) DC Clean Rivers decree, final compliance legal 2025 2030 5 Baltimore sewer decree, completion legal 2016-01 2030-12-31 2046-12-31 31 Baltimore, last four overflow structures legal 2022-07-01 2030-07-31 8.08 HRSD decree, Lafayette pump stations legal 2027-05-05 2029-05-05 2 Alexandria RiverRenew, statutory date legal 2025-07-01 2026-07-01 1 Bay nitrogen and phosphorus targets voluntary 2025 2040 15 Baltimore Harbor swimmable and fishable voluntary 2020 2030 10 Anacostia swimmable (District target) voluntary 2032 2027 −5 Mid-Bay James Island, construction start schedule 2024 2026-04 2.25 Loudoun Westpark stream restoration schedule 2027 2029-03 2.17
Download what-remains-05-schedule-movement.csv