26 of the 28 dated legal requirements ahead fall by the end of 2030; after 2030 the calendar is mostly voluntary, and 8 of 18 voluntary goals are dated 2040
Source. Higgins Strategy calendar of dated events, with the source document for each listed in the exhibit CSV; DC Water, LTCP consent decree quarterly report, Q2 2026; Chesapeake Bay Watershed Agreement, 2025.
Method. Legal: permit terms, consent-decree and statutory deadlines. Voluntary: Watershed Agreement goals, two-year milestones, partnership and nonprofit goals. The dates for revising targets and new state plans come from the Agreement and are counted as voluntary; the TMDL allocations themselves are the legal limit.
| Year | Date as given | Jurisdiction | Kind | Commitment |
|---|---|---|---|---|
| 2026 | 2026-11-04 | Maryland | Legal requirement | Montgomery County stormwater permit: 1,814 acres |
| 2026 | 2026-11-04 | Maryland | Legal requirement | Anne Arundel stormwater permit: 2,998 acres |
| 2026 | 2026-11-04 | Maryland | Legal requirement | Baltimore City stormwater permit: 3,696 acres |
| 2026 | 2026-11-04 | Maryland | Legal requirement | Baltimore County stormwater permit: 2,696 acres |
| 2027 | 2027-09-16 | Maryland | Legal requirement | Back River plant decree: digesters |
| 2027 | 2027-12-01 | Maryland | Legal requirement | Prince George’s stormwater permit: 2,137 acres |
| 2027 | 2027-12-29 | Maryland | Legal requirement | Howard County stormwater permit |
| 2027 | 2027-12-29 | Maryland | Legal requirement | Harford County stormwater permit |
| 2027 | 2027-12-29 | Maryland | Legal requirement | Frederick County stormwater permit |
| 2027 | 2027-12-29 | Maryland | Legal requirement | Charles County stormwater permit |
| 2027 | 2027-12-29 | Maryland | Legal requirement | Carroll County stormwater permit |
| 2027 | 2027-12-31 | Maryland | Legal requirement | Patapsco plant decree: grit facility |
| 2027 | 2027-07-01 | Virginia | Legal requirement | HRSD sewer decree: four interim projects |
| 2027 | 2027-07-01 | Virginia | Legal requirement | Richmond overflow Interim Plan: 10 projects |
| 2027 | 2027-12-31 | Bay-wide | Voluntary goal | End of the 2026–27 two-year milestones |
| 2027 | 2027-12-31 | Conowingo plan | Voluntary goal | Conowingo plan 2026–27 milestones |
| 2027 | 2027 | Maryland | Voluntary goal | Patuxent River Commission: wetland parks |
| 2027 | 2027 | Virginia | Voluntary goal | Virginia pay-for-outcomes pilot: 38,600 lb |
| 2028 | 2028-12-19 | DC | Legal requirement | DC stormwater permit: 1,175 acres managed |
| 2028 | 2028-05-05 | Virginia | Legal requirement | HRSD sewer decree: three interim projects |
| 2028 | 2028-07-01 | Virginia | Legal requirement | Virginia farm-practice law: earliest trigger |
| 2028 | 2028-10-31 | Virginia | Legal requirement | Virginia Phase II stormwater permit: last 60% |
| 2028 | 2028-10-31 | Virginia | Legal requirement | Falls Church permit: 1,323 lb nitrogen |
| 2028 | 2028 | Virginia | Voluntary goal | Virginia farm cost-share goal |
| 2029 | 2029-11-23 | DC | Legal requirement | Rock Creek storage tunnel in operation |
| 2029 | 2029-05-05 | Virginia | Legal requirement | HRSD sewer decree: Lafayette pump stations |
| 2030 | 2030-02-08 | DC | Legal requirement | Potomac River Tunnel in operation |
| 2030 | 2030-08 | Maryland | Legal requirement | State Highway Administration permit: 4,092 acres |
| 2030 | 2030-12-31 | Maryland | Legal requirement | Baltimore sewer decree: Phase II (current date) |
| 2030 | 2030-07-01 | Virginia | Legal requirement | Virginia farm-practice law: outside date |
| 2030 | 2030-12-31 | Virginia | Legal requirement | HRSD sewer decree: Phase I ends |
| 2030 | 2030 | Bay-wide | Voluntary goal | Underwater grasses: 90,000 acres |
| 2030 | 2030-12-31 | Bay-wide | Voluntary goal | Bay planning targets revised |
| 2030 | 2030 | Maryland | Voluntary goal | Baltimore Harbor swimmable and fishable |
| 2030 | 2030 | Maryland | Voluntary goal | Baltimore Oyster Partnership: 5 million |
| 2035 | 2035-07-01 | Virginia | Legal requirement | Richmond overflow Final Plan: 96% capture |
| 2035 | 2035 | Bay-wide | Voluntary goal | Underwater grasses: 95,000 acres |
| 2040 | 2040-12-31 | Virginia | Legal requirement | HRSD sewer decree: Phase II ends |
| 2040 | 2040 | Bay-wide | Voluntary goal | Oysters: 2,000 more reef acres |
| 2040 | 2040 | Bay-wide | Voluntary goal | Wetlands: 6,000 created, 30,000 enhanced |
| 2040 | 2040 | Bay-wide | Voluntary goal | Trees and forest buffers |
| 2040 | 2040 | Bay-wide | Voluntary goal | Underwater grasses: 100,000 acres |
| 2040 | 2040 | Bay-wide | Voluntary goal | Fish passage: 150 miles every two years |
| 2040 | 2040 | Bay-wide | Voluntary goal | Revised targets to be met under new or amended state plans |
| 2040 | 2040 | Maryland | Voluntary goal | Patuxent River restoration |
| 2040 | 2040 | Pennsylvania | Voluntary goal | Lancaster Clean Water Partners goal |