From Study XXI, Exhibit 27

All five DC Water tunnel contracts went to joint ventures with a member whose parent is headquartered abroad; the largest, a $819.7 million ceiling for the Potomac River Tunnel, went to CBNA and Halmar

Source. DC Water Board resolutions and meeting packages, 2007–2023; HRSD Commission minutes, 2022–2025; AlexRenew award as reported in Virginia DEQ report RD662 (2021); Baltimore Board of Estimates records, 2009–2025; ownership from company and parent filings.

Method. Each contract is one row from the utilities’ board records: the award value, the not-to-exceed amount (Potomac River Tunnel) or, for HRSD design-build work, the stipulated price. The Blue Plains Tunnel figure is the original award; DC Water later reported a final cost of $318.7 million. Firm totals are the summed value of the contracts shown that each firm is party to; joint-venture members are credited with the whole contract, so firm totals overlap and do not add. Ownership is current: Lane and Healy joined Webuild after the 2013 Anacostia award. Left out of the drawing and kept in the table: the two total rows, the published joint-venture split and the Blue Plains Tunnel’s final cost.

ProgramContractYearValue ($ million)Value basisJoint ventureMembersMembers with parent abroad
DC Clean Rivers tunnel program · DC Water, DistrictBlue Plains Tunnel2011330.6originalyesTraylor Bros.; Skanska; Jay Dee ContractorsSkanska
DC Clean Rivers tunnel program · DC Water, DistrictAnacostia River Tunnel2013253.9originalyesSalini Impregilo; S.A. Healy; ParsonsSalini Impregilo; S.A. Healy
DC Clean Rivers tunnel program · DC Water, DistrictTunnel dewatering pump station2013214.9originalyesPC Construction; CDM Smith
DC Clean Rivers tunnel program · DC Water, DistrictFirst Street Tunnel2013157.7originalyesSkanska; Jay Dee ContractorsSkanska
DC Clean Rivers tunnel program · DC Water, DistrictNortheast Boundary Tunnel2017580originalyesSalini Impregilo; S.A. HealySalini Impregilo; S.A. Healy
DC Clean Rivers tunnel program · DC Water, DistrictPotomac River Tunnel, Contract B2023819.7originalyesCBNA; Halmar InternationalCBNA; Halmar International
Blue Plains plant · DC Water, DistrictNitrification-denitrification reactors2007101.2originalnoUlliman Schutte
Blue Plains plant · DC Water, DistrictEnhanced nutrient removal tankage201069.5originalnoPC Construction
Blue Plains plant · DC Water, DistrictBiosolids main process train2011208.4originalyesPC Construction; CDM Smith
RiverRenew · AlexRenew, VirginiaRiverRenew tunnel system2020454.4originalyesTraylor Bros.; J.F. Shea
SWIFT and nutrient removal · HRSD, VirginiaJames River SWIFT and nutrient reduction2022534.1finalyesUlliman Schutte; Alberici
SWIFT and nutrient removal · HRSD, VirginiaNansemond nutrient reduction, Phase II2023299.2finalnoGarney
SWIFT and nutrient removal · HRSD, VirginiaNansemond recharge wells202585.9finalnoGarney
SWIFT and nutrient removal · HRSD, VirginiaNansemond SWIFT facility2025608.7finalnoGarney
Nutrient removal · Baltimore DPW, MarylandPatapsco denitrification filters2009115.7originalnoFru-Con
Nutrient removal · Baltimore DPW, MarylandPatapsco nitrification filters2012129.8originalnoFru-Con
Nutrient removal · Baltimore DPW, MarylandBack River ENR, SC 8772013263.5originalnoArcher Western
Nutrient removal · Baltimore DPW, MarylandPatapsco clarifiers, SC 994202579.9originalnoUlliman Schutte
firm total (non-additive)Garney993.8sum of whole-contract values shown3 contractsemployee-owned
firm total (non-additive)Salini Impregilo833.8sum of whole-contract values shown2 contractsWebuild, Italy
firm total (non-additive)S.A. Healy833.8sum of whole-contract values shown2 contractsLane, Webuild, Italy
firm total (non-additive)CBNA819.7sum of whole-contract values shown1 contractsBouygues, France
firm total (non-additive)Halmar International819.7sum of whole-contract values shown1 contractsASTM Group, Italy
firm total (non-additive)Traylor Bros.785sum of whole-contract values shown2 contractsfamily-owned
firm total (non-additive)Ulliman Schutte715.2sum of whole-contract values shown3 contractsownership undocumented
firm total (non-additive)Alberici534.1sum of whole-contract values shown1 contractsownership undocumented
firm total (non-additive)PC Construction492.9sum of whole-contract values shown3 contractsemployee-owned
firm total (non-additive)Skanska488.2sum of whole-contract values shown2 contractsSkanska AB, Sweden
firm total (non-additive)Jay Dee Contractors488.2sum of whole-contract values shown2 contractsfamily-owned
firm total (non-additive)J.F. Shea454.4sum of whole-contract values shown1 contractsfamily-owned
firm total (non-additive)CDM Smith423.4sum of whole-contract values shown2 contractsemployee-owned
firm total (non-additive)Archer Western263.5sum of whole-contract values shown1 contractsWalsh Group, family-owned
firm total (non-additive)Parsons253.9sum of whole-contract values shown1 contractspublicly listed
firm total (non-additive)Fru-Con245.4sum of whole-contract values shown2 contractsownership undocumented
all contracts shown5,306.9mixed: award, not-to-exceed, stipulated9 joint ventures
DC Water tunnels (five)2,141.75 joint venturesall five
Potomac River Tunnel JV split (published)CBNA 70%; Halmar 30%2023yes
Blue Plains Tunnel, final cost reported by DC Water318.7final

Download who-does-the-work-01-players-map.csv

Download SVG · CSV. Data and chart licensed CC BY 4.0.