All five DC Water tunnel contracts went to joint ventures with a member whose parent is headquartered abroad; the largest, a $819.7 million ceiling for the Potomac River Tunnel, went to CBNA and Halmar
Source. DC Water Board resolutions and meeting packages, 2007–2023; HRSD Commission minutes, 2022–2025; AlexRenew award as reported in Virginia DEQ report RD662 (2021); Baltimore Board of Estimates records, 2009–2025; ownership from company and parent filings.
Method. Each contract is one row from the utilities’ board records: the award value, the not-to-exceed amount (Potomac River Tunnel) or, for HRSD design-build work, the stipulated price. The Blue Plains Tunnel figure is the original award; DC Water later reported a final cost of $318.7 million. Firm totals are the summed value of the contracts shown that each firm is party to; joint-venture members are credited with the whole contract, so firm totals overlap and do not add. Ownership is current: Lane and Healy joined Webuild after the 2013 Anacostia award. Left out of the drawing and kept in the table: the two total rows, the published joint-venture split and the Blue Plains Tunnel’s final cost.
| Program | Contract | Year | Value ($ million) | Value basis | Joint venture | Members | Members with parent abroad |
|---|---|---|---|---|---|---|---|
| DC Clean Rivers tunnel program · DC Water, District | Blue Plains Tunnel | 2011 | 330.6 | original | yes | Traylor Bros.; Skanska; Jay Dee Contractors | Skanska |
| DC Clean Rivers tunnel program · DC Water, District | Anacostia River Tunnel | 2013 | 253.9 | original | yes | Salini Impregilo; S.A. Healy; Parsons | Salini Impregilo; S.A. Healy |
| DC Clean Rivers tunnel program · DC Water, District | Tunnel dewatering pump station | 2013 | 214.9 | original | yes | PC Construction; CDM Smith | |
| DC Clean Rivers tunnel program · DC Water, District | First Street Tunnel | 2013 | 157.7 | original | yes | Skanska; Jay Dee Contractors | Skanska |
| DC Clean Rivers tunnel program · DC Water, District | Northeast Boundary Tunnel | 2017 | 580 | original | yes | Salini Impregilo; S.A. Healy | Salini Impregilo; S.A. Healy |
| DC Clean Rivers tunnel program · DC Water, District | Potomac River Tunnel, Contract B | 2023 | 819.7 | original | yes | CBNA; Halmar International | CBNA; Halmar International |
| Blue Plains plant · DC Water, District | Nitrification-denitrification reactors | 2007 | 101.2 | original | no | Ulliman Schutte | |
| Blue Plains plant · DC Water, District | Enhanced nutrient removal tankage | 2010 | 69.5 | original | no | PC Construction | |
| Blue Plains plant · DC Water, District | Biosolids main process train | 2011 | 208.4 | original | yes | PC Construction; CDM Smith | |
| RiverRenew · AlexRenew, Virginia | RiverRenew tunnel system | 2020 | 454.4 | original | yes | Traylor Bros.; J.F. Shea | |
| SWIFT and nutrient removal · HRSD, Virginia | James River SWIFT and nutrient reduction | 2022 | 534.1 | final | yes | Ulliman Schutte; Alberici | |
| SWIFT and nutrient removal · HRSD, Virginia | Nansemond nutrient reduction, Phase II | 2023 | 299.2 | final | no | Garney | |
| SWIFT and nutrient removal · HRSD, Virginia | Nansemond recharge wells | 2025 | 85.9 | final | no | Garney | |
| SWIFT and nutrient removal · HRSD, Virginia | Nansemond SWIFT facility | 2025 | 608.7 | final | no | Garney | |
| Nutrient removal · Baltimore DPW, Maryland | Patapsco denitrification filters | 2009 | 115.7 | original | no | Fru-Con | |
| Nutrient removal · Baltimore DPW, Maryland | Patapsco nitrification filters | 2012 | 129.8 | original | no | Fru-Con | |
| Nutrient removal · Baltimore DPW, Maryland | Back River ENR, SC 877 | 2013 | 263.5 | original | no | Archer Western | |
| Nutrient removal · Baltimore DPW, Maryland | Patapsco clarifiers, SC 994 | 2025 | 79.9 | original | no | Ulliman Schutte | |
| firm total (non-additive) | Garney | 993.8 | sum of whole-contract values shown | 3 contracts | employee-owned | ||
| firm total (non-additive) | Salini Impregilo | 833.8 | sum of whole-contract values shown | 2 contracts | Webuild, Italy | ||
| firm total (non-additive) | S.A. Healy | 833.8 | sum of whole-contract values shown | 2 contracts | Lane, Webuild, Italy | ||
| firm total (non-additive) | CBNA | 819.7 | sum of whole-contract values shown | 1 contracts | Bouygues, France | ||
| firm total (non-additive) | Halmar International | 819.7 | sum of whole-contract values shown | 1 contracts | ASTM Group, Italy | ||
| firm total (non-additive) | Traylor Bros. | 785 | sum of whole-contract values shown | 2 contracts | family-owned | ||
| firm total (non-additive) | Ulliman Schutte | 715.2 | sum of whole-contract values shown | 3 contracts | ownership undocumented | ||
| firm total (non-additive) | Alberici | 534.1 | sum of whole-contract values shown | 1 contracts | ownership undocumented | ||
| firm total (non-additive) | PC Construction | 492.9 | sum of whole-contract values shown | 3 contracts | employee-owned | ||
| firm total (non-additive) | Skanska | 488.2 | sum of whole-contract values shown | 2 contracts | Skanska AB, Sweden | ||
| firm total (non-additive) | Jay Dee Contractors | 488.2 | sum of whole-contract values shown | 2 contracts | family-owned | ||
| firm total (non-additive) | J.F. Shea | 454.4 | sum of whole-contract values shown | 1 contracts | family-owned | ||
| firm total (non-additive) | CDM Smith | 423.4 | sum of whole-contract values shown | 2 contracts | employee-owned | ||
| firm total (non-additive) | Archer Western | 263.5 | sum of whole-contract values shown | 1 contracts | Walsh Group, family-owned | ||
| firm total (non-additive) | Parsons | 253.9 | sum of whole-contract values shown | 1 contracts | publicly listed | ||
| firm total (non-additive) | Fru-Con | 245.4 | sum of whole-contract values shown | 2 contracts | ownership undocumented | ||
| all contracts shown | 5,306.9 | mixed: award, not-to-exceed, stipulated | 9 joint ventures | ||||
| DC Water tunnels (five) | 2,141.7 | 5 joint ventures | all five | ||||
| Potomac River Tunnel JV split (published) | CBNA 70%; Halmar 30% | 2023 | yes | ||||
| Blue Plains Tunnel, final cost reported by DC Water | 318.7 | final |