From Study XXI, Exhibit 75

A planned Maryland acre averages $45,837 in new-practice cost; DC Water’s built green infrastructure cost $1.17 million per acre managed, 3.9 to 4.7 times its own plan

Source. MDE, October 2025, Tables 5 and 6; Anne Arundel County MS4 presentation (May 2025), slide 27; UNC Environmental Finance Center, Prince George’s County case study (2016); DC Water, Potomac River green infrastructure practicability assessment (August 2020), Table 2-8; DC Water, 2015 LTCP modification, TM7.

Method. Logarithmic scale. The items are not like for like: Maryland acres are permit credits of any practice type, Anne Arundel’s are county-stated treated acres paid on completion, the Prince George’s figure is a contract ceiling divided by base-phase acres with no published outturn, and DC Water’s are acres managed to a 1.2-inch retention standard in the combined-sewer area, with capital cost including design in nominal 2016–18 dollars against planning figures on a 2012 construction-cost basis. Anne Arundel’s $12,530 is $21.64 million, the sum of the nine cycles on slide 27, over 1,727 acres.

Item$ per impervious acreBasisSource
Anne Arundel Full Delivery, cycles 1–9 average (contracted)12,530contractedAnne Arundel County, May 2025 presentation (derived $21.6M / 1,727 acres)
Maryland MS4 plans, new practices, FY2025–26 average45,837budgetedMDE October 2025 report, Table 5
Prince George’s partnership, base-phase contract (2015)50,000contractedUNC Environmental Finance Center case study ($100M / 2,000 acres)
Maryland MS4 plans, full cost of compliance per planned acre87,113budgetedMDE October 2025 report, Tables 5 and 6
DC Water plan, Piney Branch 30% scenario (2012 dollars)249,553budgetedDC Water 2015 LTCP modification, TM7
DC Water plan, Potomac 30% scenario (2012 dollars)298,532budgetedDC Water 2015 LTCP modification, TM7
DC Water built, Rock Creek Project A (capital cost)1,165,200reportedDC Water Practicability Assessment (Aug 2020), Table 2-8