Counties’ FY2025–26 plans put a new restored acre at $45,837 on average, from $9,521 in Baltimore City to $260,013 in Howard; with maintenance and debt it is $87,113
Source. MDE, October 2025 report, Table 5 (planned acres and cost of new practices) and Table 6 (cost of compliance), FY2025–26, budgeted; per-acre values derived.
Method. Per-acre values divide planned cost by planned acres. The full cost of compliance also pays for maintenance, monitoring and debt service on earlier work, so dividing it by new acres overstates the marginal cost of an acre. Howard’s cost of compliance ($35.0 million) is below its planned cost of new practices ($51.2 million), so its second figure is the lower one.
| Jurisdiction | Planned acres | Planned cost ($) | New practices per planned acre ($) | Cost of compliance ($ million) | Cost of compliance per planned acre ($) |
|---|---|---|---|---|---|
| Baltimore City | 2,632 | 25,058,406 | 9,521 | 99.1 | 37,652 |
| Harford | 327 | 11,095,000 | 33,930 | 37.3 | 114,067 |
| Charles | 203 | 8,556,983 | 42,153 | 12.9 | 63,547 |
| Baltimore County | 1,456 | 68,433,185 | 47,001 | 76.6 | 52,610 |
| Prince George’s | 1,709 | 85,301,001 | 49,913 | 204.3 | 119,544 |
| Anne Arundel | 1,316 | 67,965,265 | 51,645 | 162 | 123,100 |
| Frederick | 396 | 20,461,398 | 51,670 | 23.6 | 59,596 |
| Carroll | 235 | 13,740,200 | 58,469 | 21.8 | 92,766 |
| Montgomery | 566 | 62,396,977 | 110,242 | 114.8 | 202,827 |
| Howard | 197 | 51,222,592 | 260,013 | 35 | 177,665 |
| All ten | 9,037 | 414,231,007 | 45,837 | 787.2 | 87,113 |