From Study XXXII, Exhibit 17

Maryland put the cost of treating an acre at $12,500 with upkeep; the state puts Ellicott City’s 2016 flood losses at upwards of $67 million

ItemPlaceKindLowHighUnitSource
Urban stormwater practices, capital onlyMaryland Phase I MS4 jurisdictionsbuild5,1555,155dollars per acre treatedMaryland Phase II WIP, Appendix C (MDE, 2012)
Urban stormwater practices, capital plus operationMaryland Phase I MS4 jurisdictionsbuild and keep12,50012,500dollars per acre treatedMaryland Phase II WIP, Appendix C (MDE, 2012)
Urban stream restoration (planning rate)Marylandrepair285285dollars per footMaryland Phase II WIP, Appendix C (MDE, 2012)
Urban stream restoration (range)Chesapeake Bay watershedrepair150400dollars per footChesapeake Bay Program, U-4 Urban Stream Restoration
Urban stream restoration (typical)Baltimore, Md. case studyrepair5001,200dollars per footKenney et al. 2012, Journal of the American Water Resources Association
Detention ponds, nitrogen equivalentBaltimore, Md. case studybuild30120dollars per foot of streamKenney et al. 2012, Journal of the American Water Resources Association
Rip-rap bank armoringBaltimore, Md. case studyrepair0120dollars per footKenney et al. 2012, Journal of the American Water Resources Association
Ellicott City flood of July 30, 2016, economic lossesHoward County, Md.damage67,000,00067,000,000dollars (upwards of)Maryland Department of the Environment, October 22, 2025
Ellicott City Safe and Sound plan, funding secured to dateHoward County, Md.repair300,000,000300,000,000dollars (more than)Howard County Government, September 10, 2025

Source. Maryland Department of the Environment, Phase II WIP Appendix C, Cost Analyses and Funding Studies (October 15, 2012); Chesapeake Bay Program, U-4 Urban Stream Restoration fact sheet (draft, March 25, 2015); Kenney, Wilcock, Hobbs, Flores and Martínez, “Is Urban Stream Restoration Worth It?,” Journal of the American Water Resources Association 48(3) (2012); Maryland Department of the Environment, news release, October 22, 2025; Howard County Government, news release, September 10, 2025.

Method. Each row is the source’s own figure in its own year’s dollars; rows are not adjusted for inflation or added together.