In Prince William’s 2026 plan, stream restoration costs $8,371 to $14,000 per pound of annual nitrogen reduction; four of five pond retrofits cost $3,277 to $8,507
Source. Prince William County, draft Phase II Chesapeake Bay TMDL action plan (revised July 6, 2026), Appendix C, budgeted.
Method. The plan’s own cost per pound of total nitrogen removed per year. The $50,000 retrofit is Pond #62, at 7 lb a year. Appendix E gives Middle Dewey’s Phase 1 a cost of $9,957,400 against $6,244,800 in Appendix C; Appendix C is used.
| Project | Type | Implementation FY | Cost ($) | $ per lb of nitrogen a year |
|---|---|---|---|---|
| Middle Dewey's Phase 1 | Stream | 2026 | 6,244,800 | 8,371 |
| Chinn Park - Stream | Stream | 2025 | 2,520,000 | 9,509 |
| Powells Creek Phase 2 | Stream | 2024 | 8,400,000 | 14,000 |
| SWM Facility #416 Retrofit | Retrofit | 2026 | 850,000 | 3,277 |
| SWM Facility #521 Retrofit | Retrofit | 2026 | 385,100 | 3,300 |
| SWM Facility #460 Retrofit | Retrofit | 2026 | 335,960 | 4,403 |
| Chinn Park - SWM Facility #5749 Retrofit | Retrofit | 2025 | 750,000 | 8,507 |
| SWM Facility #62 Retrofit | Retrofit | 2025 | 345,000 | 50,000 |
Download every-impervious-acre-09-cost-per-pound-prince-william.csv