From Study XXI, Exhibit 31

Twelve of 13 HRSD contracts that returned to the Commission grew in value, including added scope, by a median 14.2%; the largest rise, at Surry, is mostly a change in scope

Source. HRSD Commission minutes, January 2022–August 2026 (page cited for each contract in the CSV).

Method. Growth in contract value, including added scope, from the first approved figure to the latest revised or stipulated figure in the minutes; construction-manager-at-risk contracts are excluded. The sample holds only contracts that came back to the Commission, so 12 of 13 is not an overrun rate, and latest figures are to date for open projects. Five design-build contracts start from a Contract Cost Limit, a cap set before design; eight start from an award or bid. From its stipulated price rather than its cost limit, the Eastern Shore contract grew 73.6%. Left out of the drawing and kept in the table: the median row.

ContractChange (%)Design-build, from cost limitFirst and latest figures
Surry Hydraulic Improvements and Interceptor Force Main443nofirst 8,978,000 (date n/a) to latest 48,746,765 (2022-11-22); HRSD minutes, page 19
Eastern Shore Infrastructure Improvements, Transmission Force Main Phase I152.8yesfirst 15,764,700 (2021-07-27) to latest 39,860,424 (2024-04-23); HRSD minutes, page 7
Sanitary Sewer Replacement 1950 Part 227.7nofirst 17,274,540 (2022-11-22) to latest 22,064,526 (2024-09-24); HRSD minutes, page 39
Lucas Creek Pump Station Replacement26.8nofirst 19,285,068 (2022-04-26) to latest 24,446,995 (2024-12-17); HRSD minutes, page 41
Solids System Improvements for Army Base Treatment Plant, multiple hearth incine26.7nofirst 4,273,000 (2022-07-26) to latest 5,413,022 (2025-08-26); HRSD minutes, page 53
Lee Avenue-Wesley Street Horizontal Valve Replacement19.3nofirst 6,280,000 (2024-09-24) to latest 7,489,842 (2025-07-22); HRSD minutes, page 42
Nansemond Treatment Plant Advanced Nutrient Reduction Improvements Phase II14.2yesfirst 262,102,000 (2022-02-22) to latest 299,233,922 (2023-02-28); HRSD minutes, page 18
James River SWIFT Facility and James River Treatment Plant Advanced Nutrient Red14.1yesfirst 468,073,039 (2021-01-26) to latest 534,098,839 (2022-05-24); HRSD minutes, page 25
Park Avenue Pump Station Replacement12.2nofirst 11,414,000 (2022-05-24) to latest 12,811,680 (2026-08-25); HRSD minutes, page 32
46th Street Diversion Sewer Rehabilitation/Replacement9.8nofirst 9,419,297 (2022-06-28) to latest 10,338,290 (2025-06-24); HRSD minutes, page 40
York River System Isolation Valve Installation and Replacement8.6nofirst 6,874,630 (2022-09-27) to latest 7,469,002 (2024-02-27); HRSD minutes, page 36
Nansemond SWIFT Facility6yesfirst 574,000,000 (2024-04-23) to latest 608,717,209 (2025-07-22); HRSD minutes, page 242
Boat Harbor Treatment Plant Transmission Force Main Section 1, subaqueous portio−1.7yesfirst 144,309,720 (2022-04-26) to latest 141,862,737 (2023-05-23); HRSD minutes, page 20
median of 1314.212 of 13 grew

Download who-does-the-work-05-hrsd-contract-value-growth.csv

Download SVG · CSV. Data and chart licensed CC BY 4.0.