Virginia’s mandatory farm practices cannot take effect before July 1, 2028, and each underfunded year delays them, to July 1, 2030 unless funding fell short
Source. Code of Virginia § 62.1-44.119:1; JLARC Report 620 (commission draft); EPA, 2025 Assessment.
Method. The extension adds one year for each calendar year the state did not fully fund the cost-share need.
| Date | Event | Set by |
|---|---|---|
| Jul 1, 2023 | Extension clock starts | Virginia law (Va. Code 62.1-44.119:1) |
| Dec 31, 2025 | Original Phase III date passes | Bay partnership / EPA |
| Jun 30, 2027 | VACS plan: practices in place (end FY27) | JLARC description of VACS needs assessment |
| Jul 1, 2028 | Earliest joint determination | Virginia law (Va. Code 62.1-44.119:1) |
| Jul 1, 2030 | Outside date unless underfunded | Virginia law (Va. Code 62.1-44.119:1) |
| 2030 | New Bay targets and WIPs due | Bay partnership / EPA |
| 2040 | Reductions under new WIPs met | Bay partnership / EPA |